Israeli Legislation.com

Water and Sewerage Corporations (Determination of Licence Conditions concerning Engineering Standards) Rules, 5777-2017

כללי תאגידי מים וביוב (קביעת תנאים ברישיון לעניין אמות מידה הנדסיות), תשע"ז-2017

Published: 2017-02-22Consolidated Hebrew text as of 2026-09-15 · Last amended 2023-10-30
Premium
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More

This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.

Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.

The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.

This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.

By virtue of its authority under sections 21a, 26(b)(2), 51(c), 99 and 112 of the Water and Sewerage Corporations Law, 5761-2001 (hereinafter – the Law), in consultation with the Commissioner pursuant to section 99 of the Law and after the provisions of section 107 of the Law have been complied with, the Council of the Government Authority for Water and Sewerage prescribes these Rules (hereinafter – the Rules):

Chapter I: General Provisions

Definitions§

1.

In these Rules –

"pressure zone" – an area in the water system in which the water has a similar hydraulic head;

"measurement zone" – a defined area of a water system in which the quantity of water entering and exiting it can be measured, as well as the water system as a whole;

"the website" – the website of the Government Authority, the address of which is www.water.gov.il;

"the Commissioner" – as defined in the Law, or a person whom he has authorised for the purpose of issuing instructions pursuant to these Rules;

"water pressure regulation" – dynamic pressure regulation and static pressure regulation;

"dynamic pressure regulation" – the variation of water pressure at a particular point in the water system according to the water flow rate at that point or according to the water pressure at other points in the water system that receive water from it;

"static pressure regulation" – the limitation of the upper limit and the lower limit of water pressure at a particular point in the water system;

"asset ratio" – the ratio between the total depreciated replacement value and the full replacement value of the water and sewerage systems of the company;

"total depreciated replacement value" – as defined in the Cost Calculation Rules;

"full replacement value" – as defined in the Cost Calculation Rules, plus the cost of constructing material assets that the Commissioner has decided are absent from the water and sewerage systems;

"Cost Calculation Rules" – the Water and Sewerage Corporations (Calculation of the Cost of Water and Sewerage Services and the Construction of a Water or Sewerage System) Rules, 5770-2009;

"peak day quantity" – the maximum quantity of water supplied to the water system in any settlement within the company's area, including water that the company itself produced, during one day in the preceding year, and in the absence of data regarding the quantity of water as aforesaid – 0.04% of the quantity of water supplied in the preceding year for all purposes except agriculture plus 0.08% of the quantity of water supplied for agricultural purposes in that year;

"ring water system" – a water system that enables water to flow from at least two directions at every point;

"GIS system" – a computerised system for the documentation of geographic information (Geographic Information System);

"infrastructure works supervisor" – as the term is used in section 25(a);

"procedure" – a procedure that a company is required to establish pursuant to these Rules;

"night consumption" – the smallest quantity of water measured at the entrance to a measurement zone during two consecutive hours in the period between midnight and 05:00 the following morning;

"water loss" – as the term is used in section 10(a);

"water loss rate" – as the term is used in section 10(b).

Status of the Rules§

2.

These Rules form part of the licence conditions of a company that has been granted a licence pursuant to section 15 of the Law.

Chapter II: Water Services

Reliability of Water Supply§

3.
(a)In this section –

"appropriate measures" – including one or more of the following:

(1)installation of alternative pumps and systems at pumping stations and water boreholes;
(2)installation of an alternative source of electricity supply at pumping stations and water boreholes;
(3)connection of the town to at least two independent water sources;
(4)storage in a volume of not less than three times the peak day quantity, or such other volume as the Commissioner may direct in a particular case;
(5)construction of the water system, in whole or in part, as a ring water system;

"malfunction" – a disruption or interruption in the normal operation of water pipes or other installations in the water system, as well as a disruption or interruption in the supply of water to the water system.

(b)A company shall ensure that its daily water supply capacity in every settlement within the company's area shall not, in the absence of malfunctions, fall below the peak day quantity, without making use of private extraction equipment.
(c)A company shall take appropriate measures to ensure, at all times, that in the event of a single malfunction, its water supply capacity for one day in every settlement within the company's area shall not fall below 70% of the peak day quantity.
(d)If the Commissioner is of the opinion that the measures taken by a company are insufficient to ensure water supply capacity pursuant to this section, he may direct the company to take such additional measures as he shall direct, after having given it an opportunity to present its arguments.

Restrictions on Water Pressure§

4.
(a)The water flow pressure at the point at which water is transferred to the consumer's premises of the company shall not fall below 2.5 atmospheres and shall not exceed 5 atmospheres, at any time.
(b)Notwithstanding the provisions of subsection (a), the Commissioner may approve, in a reasoned written decision, a company's supply at water pressures higher than those specified in that subsection, on a permanent basis or for a specified period of time, if he finds that the benefit of such excess to the water economy outweighs its disadvantages and that the excess will not cause additional costs to the company, harm consumers or affect the supply of water to them; and he may reject such a request on other grounds as well.

Establishment of Procedures for Water Pressure Regulation§

5.

A company shall establish procedures for the circumstances and areas in which it shall carry out water pressure regulation and for the method of carrying it out; the procedures shall ensure that water pressures in the water system do not fall below or exceed the pressures prescribed in section 4.

Taking of Reasonable Measures to Prevent Water Waste§

6.
(a)A company shall take reasonable measures to prevent water waste.
(b)A company in which the water loss rate in a settlement within its area in the preceding year exceeded 10% shall take the following measures in the area of that settlement to prevent water waste:
(1)continuous monitoring of the quantity of water entering and exiting each measurement zone;
(2)examination of water loss in each of the measurement zones within its area at least once every two months;
(3)establishment of procedures for investigating anomalies in the supply of water to a measurement zone compared with the quantity of water normally supplied to that zone;
(4)establishment of procedures for investigating anomalies in night consumption in a measurement zone compared with the usual night consumption in that zone;
(5)establishment of procedures for cases in which a suspicion of the existence of a water leak shall be examined and the manner of conducting the examination;
(6)establishment of procedures for examining water loss at a frequency greater than once every two months in a measurement zone in which water loss greater than 130% of the recognised water loss for the corporation pursuant to section 12 of the Cost Calculation Rules has been measured.
(c)Notwithstanding the provisions of subsections (a) and (b), the Commissioner may require a company to take additional measures to prevent water waste if he finds that there exist within the company's area zones in which water loss or water waste at rates that necessitate further action to ensure the efficient use of water exists.

Taking of Reasonable Measures to Reduce Water Interruptions§

7.

A company shall take reasonable measures to reduce water interruptions, and in particular unexpected interruptions; for this purpose, "unexpected interruption" – a water interruption of which it was not possible to give advance notice to consumers.

Installation of Water Meters in a New Property§

8.

A company shall establish procedures for the installation of water meters in a new property, which shall ensure the correct attribution of a water meter to a consumer and the correct recording of water charges in the company's information systems.

Chapter III: Estimation of Water Loss

Definitions§

9.

In this Chapter –

"measurement day" – a day for which the company has carried out an estimation of a water meter reading;

"incoming water quantity" – the quantity of water that the company produced or that was supplied to it during the measurement period, and in a measurement zone that is not the water system as a whole – the quantity of water that entered the measurement zone less that which exited it to other zones, during the measurement period;

"outgoing water quantity" – the quantity of water that the company supplied by measurement during the measurement period;

"calculation period" – the number of days between the date on which the water meter reading was last read before the measurement day and the measurement day;

"measurement period" – the period in respect of which water loss is estimated;

"reading period" – the number of days between the date on which the water meter reading was last read before the measurement day and the date on which the water meter reading was first read after the measurement day.

Calculation of Water Loss§

10.
(a)Water loss in a measurement zone shall be calculated according to the difference between the incoming water quantity to the measurement zone and the outgoing water quantity from the measurement zone during the measurement period.
(b)The water loss rate in a measurement zone shall be calculated according to the ratio between the water loss calculated pursuant to subsection (a) and the incoming water quantity in the measurement zone during the measurement period.

Calculation of Incoming Water Quantity§

11.
(a)A company shall calculate the incoming water quantity according to the sum of the differences between the water meter reading at a particular time on the day of commencement of the measurement period and the water meter reading at the same time on the day following the end of the measurement period –
(1)in the water system as a whole – in all water meters measuring the water supplied to the company and the water it produces;
(2)in another measurement zone – in all water meters measuring the water supplied to the measurement zone from the measurement zone.
(b)Where a company does not have remote reading facilities for a water meter, the company shall read the water meter on the day of commencement of the period and on the day following the end of the period.

Calculation of Outgoing Water Quantity§

12.
(a)A company shall calculate the outgoing water quantity according to the sum of the differences between the estimated water meter reading on the day of commencement of the measurement period and the estimated water meter reading on the day following the end of the measurement period, in all water meters measuring the water that the company supplies to its consumers.
(b)Where a company supplied water to a consumer without measurement and sent that consumer a charge for that supply – the quantity of water in respect of which such a charge was sent shall be added to the total outgoing water quantity.

Estimation of a Water Meter Reading§

13.
(a)An estimation of a water meter reading on a measurement day shall be equal to the water meter reading last read before the measurement day, plus a proportionate part of the quantity of water measured during the reading period, according to the ratio between the calculation period and the reading period.
(b)Where the company carried out a consumption estimation for a water meter in a measurement zone, in lieu of reading a water meter reading, pursuant to section 8(b) of the Water and Sewerage Corporations (Standards and Provisions concerning the Level, Standard and Quality of Services that a Company is Required to Provide to its Consumers) Rules, 5771-2011, it shall calculate the water meter reading on the measurement day according to that consumption estimation.
(c)If the company has remote reading facilities for a water meter, the company shall read the water meter reading on the measurement day.

Quantity of Water in the Event of Addition, Removal or Replacement of a Water Meter§

14.
(a)Where a company added or removed a water meter during the measurement period, the quantity of water measured by that water meter shall be calculated from the day of commencement of the period until the removal of the water meter or from the installation of the water meter until the day following the end of the period, as the case may be.
(b)Where a company replaced a water meter during the measurement period with another water meter, it shall calculate the quantity of water as the sum of the quantities of water measured by those water meters.

Chapter IV: Sewerage Services

Reliability of Sewage Reception§

15.
(a)In this section –

"appropriate measures" – including one or more of the following:

(1)ensuring the existence of adequate gradients in gravity sewer lines;
(2)installation of alternative pumps and systems at pumping stations;
(3)installation of an alternative source of electricity supply at pumping stations;
(4)maintenance of pumping equipment available for the installation of a bypass and for pumping sewage;
(5)maintenance of available spare parts to ensure the normal operation of the sewerage system;
(6)in sensitive pressure mains – construction of at least two parallel sewage disposal systems;

"sensitive pressure main" – a pressure main with a flow rate of 2,000 cubic metres per day or whose diameter exceeds 10 inches, located in a sensitive area;

"sensitive area" – an area in the sewerage system from which sewage overflow may cause it to flow into a surface water body, the sea or the area of a wellhead protection zone of a drinking water borehole established pursuant to the Public Health (Sanitary Conditions for Drinking Water Boreholes) Regulations, 5755-1995;

"malfunction" – a disruption or interruption in the normal operation of central sewer pipes or other installations in the sewerage system, not being a pipe.

(b)A company shall ensure that the sewage reception capacity of the sewerage system in every settlement within its area shall not fall below the existing or planned sewage flow rate according to the company's master plan for each settlement and according to actual development of the settlement.
(c)A company shall take reasonable measures to ensure, at all times, that in the event of a single malfunction, its sewage reception capacity in every settlement within its area shall not fall below the sewage flow rate, and to ensure the reduction of environmental hazards in the event of a malfunction in a sensitive pressure main.
(d)If the Commissioner is of the opinion that the measures taken by a company are insufficient to ensure sewage reception capacity pursuant to this section, he may at any time direct the company to take such additional measures as he shall direct, after having given it an opportunity to present its arguments.

Connection of a Consumer to the Sewerage System§

16.

A company shall enable a consumer to connect to the sewerage system in a manner that does not require the consumer to install a pumping system to a public pressure main.

Mapping of Drainage Connections to the Sewerage System§

17.
(a)A company shall prepare a plan for the identification of connections of a stormwater drainage system to its sewerage system; in determining the order of priorities for such a plan, the company shall give priority to the identification of connections of urban drainage infrastructure and to the identification of areas in which there is a significant contribution of rainwater to the quantity of water flowing in the sewerage system.
(b)Where a company identified such a connection – it shall notify the owner of the real property thereof and may require the property owner to construct a system for the disposal of rainwater that is not connected to the sewerage system.
(c)Where a company notified the owner of real property of his obligation to disconnect a rainwater disposal system from his premises from the sewerage system and the owner of the real property did not act as aforesaid, the company may charge the owner of the real property a payment for the treatment of water added to the public sewerage system; where a condominium is connected to the sewerage system, the company shall charge all the residents of the building with the said payment.

Flushing and Filming of Gravity Sewer Lines§

18.
(a)A company shall prepare and implement a plan for the flushing and filming of the gravity sewer lines it uses for the provision of sewerage services, as detailed below, according to the dates specified alongside them:
(1)lines whose diameter exceeds 12 inches – at least once every 5 years;
(2)lines whose diameter is between 6 inches and 12 inches – at least once every 15 years; and in respect of lines that continue to form part of a sewerage system after the expiry of the maintenance period prescribed in the Schedule to the Water (Prevention of Water Pollution) (System for the Conveyance of Sewage) Regulations, 5772-2011 – at least once every 10 years.
(b)Notwithstanding the provisions of subsection (a), a company shall flush and film annually sewer lines in which one or more of the following conditions exist:
(1)more than 7 blockages occurred in them in the preceding year in a single section whose length is less than 500 metres;
(2)more than 3 blockages occurred in them in each of the three preceding years in a single section whose length is less than 500 metres.

Obligation to Establish a Facility for Emptying Sewage Tanker Vehicles§

19.

A company shall ensure that within its sewerage system or within a distance not exceeding 20 kilometres from its boundaries there is a facility for emptying sewage tanker vehicles transporting sanitary wastewater, which enables the reception and separation of solid waste from liquid waste.

Page 1 of 3

Read the entire law on one page — continuous text, no page breaks, plus formal citations.

RegulationsAdministrative Law

כללי תאגידי מים וביוב (קביעת תנאים ברישיון לעניין אמות מידה הנדסיות), תשע"ז-2017

Water Sewerage Corporations Rules 2017

Water and Sewerage Corporations Engineering Standards

Taagidei Mayim Uveavuv 5777

Engineering Standards Licence Conditions Water

Water Corporation Licence Engineering Standards

Sewerage Corporations Licence Rules 2017

Water Utilities Engineering Standards Regulations

Mayim Uveavuv Engineering Standards 2017