Work Safety (Construction Works) Regulations, 5748-1988

תקנות הבטיחות בעבודה (עבודות בניה), תשמ"ח-1988

Published: 1988-02-04Consolidated Hebrew text as of 2026-10-16 · Last amended 2020-05-21
Premium
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More

This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.

Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.

The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.

This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.

Chapter II: Work Platforms and Passageways

Preparation of a Work Platform and a Passageway§

8.
(a)Every work platform or passageway shall be suitably installed for the purpose for which it is intended and in a manner that prevents their collapse, or their full or partial breakage, or the fall of a person or object therefrom.
(b)The supports for the work platform and the passageway shall be made of suitable and defect-free material; for this purpose, bricks, blocks, barrels or lying pipes shall not be used as supports.

Fencing§

9.
(a)A construction contractor shall install fencing on every work platform and passageway from which a person or object could fall from a height exceeding two metres, provided that the fencing includes a handrail, a midrail and a toeboard and has been installed in accordance with an engineering plan.
(b)The obligation to install a midrail as referred to in sub-regulation (a) shall not apply if the vertical opening below the guardrail does not exceed 50 centimetres.
(c)A works manager shall supervise that the installation of the fencing as referred to in sub-regulation (a) conforms with the engineering plan, and if it does not conform with it, he shall halt the installation of the fencing and shall not resume it as long as the installation of the fencing does not conform with the engineering plan.
10.§

(Repealed — תשפ״ו)

Maintenance of Handrail, Midrail and Toeboards§

11.
(a)Handrails, midrails and toeboards shall be in good condition for as long as there is any continuing need for the work platform or passageway for which they were installed.
(b)If there is a necessity to move materials, it is permissible to remove them for the period of time required for that operation only, and while taking the measures necessary to prevent a person or material from falling.

Special Fencing Measures§

11a.

A regional labour inspector may approve special fencing measures, even if they do not conform to the requirements of regulation 9, if, in his opinion, those measures afford protection against the fall of a person or material from a platform.

Access to Work Platforms§

12.

Wherever a person needs to stand, work or pass, safe means of access shall be installed.

Floor and Supports for a Passageway§

13.
(a)A passageway shall be made of boards that are close together and connected to one another in a manner that prevents their displacement, and its width shall be at least 60 centimetres; the thickness of the floor boards shall be adapted to the maximum load that may be placed upon it.
(b)
(1)The transverse supports of the passageway shall be straight, installed horizontally and firmly connected to the rails and uprights;
(2)a transverse support made of wood shall have a cross-sectional area of at least 50 square centimetres and its narrow dimension shall not be less than 4.5 centimetres;
(3)a transverse support made of metal shall have a strength equivalent to that required under paragraph (2);
(4)the distance between the transverse supports shall be adapted to the maximum load to which the floor is liable to be subjected but shall not exceed 2 metres.

Gradient of a Passageway§

14.
(a)The gradient of a passageway shall not exceed the ratio of 1 vertical to 1.5 horizontal.
(b)If the gradient of a passageway exceeds the ratio of 1 vertical to 4 horizontal, treads shall be installed along the passageway at equal intervals of 30 to 35 centimetres across the full width of the passageway and shall be properly maintained, but it is permissible to leave in the centre of the passageway a track of at most 10 centimetres free of treads, for the passage of a wheelbarrow.

Removal of Obstacles§

15.

A work platform, passageway, floor and any other place up to a height of 2 metres in which a person is present or through which a person passes shall be free of protruding nails, binding wires and any other protruding object or obstacle with which a person might collide.

Chapter III: Scaffolding

Section A: General

Obligation to Install Scaffolding§
16.
(a)If it is impossible to carry out work safely while standing on the ground or on a permanent structure, the construction contractor shall provide stable scaffolding, suitable to the nature of the work and in the quantity required, so as to enable work to be carried out safely.
(b)The construction contractor shall not plan, erect, install, use, dismantle scaffolding or make any alteration to it unless the planning, erection, installation, use and dismantling of the scaffolding or the making of the alteration thereto are carried out in accordance with the provisions of these Regulations and in accordance with the responses provided to risks in the erection of scaffolding in the safety plan and in accordance with the scaffolding manufacturer's instructions, and if it has been prescribed under these Regulations that an engineering plan is required or that the operation shall be carried out by means of a professional builder for tube-and-fitting scaffolding or a scaffolding erection planner, as the case may be, the construction contractor shall carry out the operation in accordance with the engineering plan or by means of such person, as the case may be.
(c)The construction contractor shall attach to the scaffolding he provides under these Regulations the manufacturer's instructions in writing in the Hebrew language, and if the scaffolding was manufactured outside Israel – also in the English language.
(d)The works manager shall attach the manufacturer's instructions as referred to in sub-regulations (b) and (c) to the general log at the construction site.
Supervision by a Professional Builder for Tube-and-Fitting Scaffolding§
17.
(a)A construction contractor shall not erect, install, dismantle or make any alteration to tube-and-fitting scaffolding whose height exceeds 6 metres except in the presence and under the direct supervision of a professional builder for tube-and-fitting scaffolding.
(b)A professional scaffolding builder shall not approve the installation, dismantling or alteration of tube-and-fitting scaffolding except in accordance with the provisions of this Section and Section B and the scaffolding manufacturer's instructions, and if the scaffolding is required under these Regulations to be planned by a scaffolding erection planner or by an engineering plan – also in accordance with the instructions of the scaffolding erection planner or the engineering plan, as the case may be.
Special Scaffolding§
17a.
(a)A construction contractor shall not erect, install or dismantle special scaffolding and shall not make any alteration thereto, except in accordance with an engineering plan.
(b)(Repealed)
(c)(Repealed)
Materials for Scaffolding§
18.
(a)For the installation of scaffolding, the construction operator shall supply suitable materials and components of good quality, free from defect and in sufficient quantity, and once such materials and components have been supplied they shall be used.
(b)Timber used for the installation of scaffolding shall be free from bark, paint and protruding nails, whether bent or unbent, and nothing shall be done to conceal defects therein.
(c)Metal used for scaffolding shall be free from flaking rust.
(d)Timber boards used for the installation of scaffolding that are liable to split on account of the condition of the fibres shall be protected against such splitting.
Inspection and Storage of Materials§
19.
(a)The works manager shall inspect the components intended for the installation of scaffolding before use thereof and shall reject any component that is not suitable.
(b)If a component has been rejected as referred to in sub-regulation (a), the works manager shall order its removal from the construction site and shall record his order in the general log.
(c)A component intended for scaffolding shall be kept separately from any other material or component.
Inspection of Scaffolding§
20.
(a)The works manager shall inspect every scaffolding unit to determine its stability and suitability for the purpose for which it is intended.
(b)The inspection under sub-regulation (a) shall be carried out upon the installation of the scaffolding and before its use has commenced, and if the scaffolding was built under these Regulations by a professional builder for tube-and-fitting scaffolding – together with the professional builder for tube-and-fitting scaffolding who built the scaffolding; a works manager shall also carry out an inspection as referred to in sub-regulation (a) –
(1)at least once every seven days;
(2)after every work stoppage of three days or more;
(3)after every work stoppage of one day or more due to rain or wind;
(4)after every alteration made to the scaffolding that has come to his knowledge.
(c)The works manager shall record in the general log at the construction site a report on every scaffolding inspection and shall bring the record to the attention of the construction contractor. This provision shall not apply to scaffolding from which no person is liable to fall to a depth exceeding 2 metres and to trestle scaffolding.
Structure of Scaffolding§
21.

Every scaffold shall be properly installed for the purpose for which it is intended and in a manner that prevents its collapse or the fall of a person or object from it.

Defective Scaffolding§
22.

If the work manager finds upon inspection of the scaffold that it is not suitable for the purpose for which it is intended, or that it has been assembled contrary to the manufacturer's instructions, or that the provisions of these Regulations have not been complied with in respect of it, the scaffold shall not be used until it has been properly repaired to the satisfaction of the work manager.

Alterations to Scaffolding§
22a.

No person shall make any alteration to tube-and-fitting scaffolding, including the removal of a part thereof, unless he is a professional builder for tube-and-fitting scaffolding or unless he does so pursuant to the written instruction of a professional builder for tube-and-fitting scaffolding; if an alteration as aforesaid has been made, the person who carried out the alteration shall notify the works manager immediately upon its completion.

Dismantling of Scaffolding§
23.
(a)Dismantling of scaffolding shall be carried out gradually from top to bottom, in all its parts, such that at all times the integrity and stability of the remaining part are maintained.
(b)From the place where scaffolding is being dismantled, all persons other than those directly engaged in carrying out the dismantling shall be removed.
(c)Parts of the scaffolding shall be lowered with care and shall not be thrown from any height whatsoever.
Lifting Installations on Scaffolding§
24.

No lifting installation shall be installed on scaffolding or adjacent to it, nor shall such an installation be used, unless:

(1)prior to the installation of the lifting installation on the scaffolding, a scaffolding erection planner has examined the effect of the installation of the lifting installation on the scaffolding on the stability of the scaffolding, and has prescribed instructions for the reinforcement of the scaffolding and for the use of the lifting installation;
(1a)a scaffolding erection planner has confirmed the fulfilment of the requirements in paragraph (1) and shall deliver his confirmation to the construction contractor;
(2)a partition has been installed or appropriate measures have been taken to prevent harm to the scaffolding or to a person on the scaffolding by the lifting installation or the material being raised or lowered by means of it.
Storage of Materials§
25.

No materials shall be kept on a scaffold to the extent of causing overloading, impairing the balance, or beyond what is necessary for the execution of current work.

Scaffold Floor§
26.
(a)A scaffold floor shall be made of platforms of suitable material installed in a manner that prevents their displacement from their position during use of the scaffold.
(b)A scaffold floor shall not serve as a support for any part of another scaffold.
Width of Scaffold Floor§
27.

The width of a scaffold floor shall be adapted to the purpose for which the scaffold is intended and shall be at least –

(1)60 centimetres – if the floor serves as a standing or sitting place for persons and no materials are kept on it;
(2)80 centimetres – if the floor also serves for the keeping of materials;
(3)130 centimetres – if stones are dressed on the floor or are otherwise worked on it.
Scaffold Floor at a Corner§
28.

The scaffold floor shall be extended beyond the corner of the structure by at least the width of the floor.

Material for Flooring§
29.

Platforms used for flooring –

(1)their width shall be at least 15 centimetres; however, platforms with a width of not less than 10 centimetres may be used if they are permanently joined to one another;
(2)if they are made of timber, their thickness shall be appropriate to the distance between the width supports and the maximum load, but shall not be less than 2.5 centimetres;
(3)if they are made of plywood, their thickness shall not be less than 2.2 centimetres;
(4)if they are not made of timber or plywood, they shall have a strength equivalent to the strength required for platforms as referred to in paragraphs (1) to (3).
Installation of Floor Platforms§
30.
(a)A platform of a scaffold floor shall not project beyond a support by more than four times the thickness of the platform, and no platform shall overlap another platform except to the extent necessary, provided that suitable arrangements have been made to facilitate the movement of wheelbarrows and to prevent a person from slipping.
(b)Every platform shall be laid on at least three bearers unless excessive deflection as a result of overloading is prevented.
(c)Floor platforms shall be close to one another with a gap not exceeding 1.5 cm, in a manner that prevents objects from falling.
Gap between scaffolding and wall§
31.
(a)The gap between the floor of scaffolding that is not suspended scaffolding and the wall shall not exceed 30 centimetres; where the work is performed in a seated position, the gap shall not be less than 25 centimetres and shall not exceed 30 centimetres.
(b)If in the circumstances of the case it is necessary that the gap exceed what is stated in sub-regulation (a), a handrail, midrail and toeboards shall also be installed on the side of the scaffolding facing the wall of the structure.
Use of Ladder Scaffolding§
32.

No person shall use ladder scaffolding for any purpose whatsoever.

Ladders between Scaffold Levels§
33.
(a)In a scaffold with more than one level, access ladders shall be installed from the ground or from another safe support to the lowest level and between each level.
(b)Ladders as referred to in sub-regulation (a) shall be properly secured to the scaffold and shall be maintained until the floors are dismantled.
(c)The openings in the scaffold floor through which the ladders pass shall be overlapping and on their inner side an upright shall be installed from level to level for safe handhold.

Section B: Upright Scaffolding

Upright Scaffolding§
34.
(a)A construction operator shall not erect or use upright scaffolding unless it meets all the requirements of this regulation:
(1)the scaffolding meets the requirements of the Israeli scaffolding standard;
(2)every component of the scaffolding has been permanently marked by the scaffolding manufacturer with markings that include the following particulars: the name of the manufacturer, the model of the scaffolding, the date of manufacture;
(3)the construction operator holds a test certificate from an approved laboratory within the meaning of section 12(a) of the Standards Law, 5713-1953, attesting that the model of the scaffolding meets the requirements of the Israeli scaffolding standard; such a certificate shall be required whether the scaffolding was manufactured in Israel or imported from outside Israel;
(4)a copy of the test certificate referred to in paragraph (3) has been attached to the general register located at the site on which the scaffolding is installed.
(b)Where a provision in these Regulations relating to upright scaffolding conflicts with a provision laid down in the Israeli scaffolding standard, the provisions laid down in the standard shall prevail.
(c)Uprights and platforms manufactured up to the end of six months from the date of publication of the Work Safety (Construction Works) (Amendment) Regulations, 5779-2019, may be marked by their manufacturer with the name of the manufacturer and the model according to which they were manufactured, if the manufacturer has received approval from an approved laboratory within the meaning of section 12(a) of the Standards Law for that model in respect of an Israeli scaffolding standard, even if the approval was granted after the date of their manufacture, and if so done the marking shall be deemed to have been made in accordance with the provisions of sub-regulation (a)(2).
Foundation of Upright Scaffolding§
35.
(a)The surface on which upright scaffolding is to be erected shall be cleared, levelled and compacted and shall not contain, or in its immediate vicinity, depressions or voids that may endanger its stability.
(b)Where scaffolding is erected on fill ground, its base surface shall be properly compacted before its erection.
(c)The surface on which the scaffolding is to be erected shall be drained in a manner that prevents the accumulation of water, and there shall not be on it or in its vicinity a water tap or a drainage pipe outlet of the structure.
36.§

(Repealed — תשפ״ו)

37.§

(Repealed — תשע״ט)

38.§

(Repealed — תשפ״ו)

39.§

(Repealed — תשפ״ו)

40.§

(Repealed — תשפ״ו)

41.§

(Repealed — תשפ״ו)

42.§

(Repealed — תשפ״ו)

43.§

(Repealed — תשפ״ו)

44.§

(Repealed — תשפ״ו)