Work Safety (Construction Works) Regulations, 5748-1988
תקנות הבטיחות בעבודה (עבודות בניה), תשמ"ח-1988
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More
This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.
Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.
The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.
This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.
Chapter VII: Prefabricated Construction
Strength of Component§
A construction operator is responsible for ensuring that a prefabricated component is of adequate strength and rigidity and is such that its integrity is ensured during its unloading at the site, its lifting, transportation or assembly at the site.
Lifting devices§
Unloading and Storage§
Assembly of Prefabricated Components§
Lifting of a Prefabricated Component in Dangerous Weather Conditions§
A prefabricated component shall not be lifted when a wind is blowing that is liable to endanger those handling it or those in its vicinity.
Devices for Fencing§
A construction operator is responsible for ensuring that a prefabricated component that is to serve as a work platform during the erection of the structure contains anchors or other suitable devices that will enable the installation of means for preventing a person from falling, as required under regulations 9 and 11.
Chapter VIII: Erection of Metal Structures
Erection of a metal structure§
Covering of Intermediate Levels§
(Repealed — תשפ״ו)
(Repealed — תשפ״ו)
(Repealed — תשפ״ו)
Chapter IX: Excavations and Earthworks
Prevention of Collapse§
Sides of Excavation or Fill§
Excavation by Machine§
The obligation to install shoring or the obligation to take other measures to prevent the collapse of the walls does not apply to excavation carried out by means of a machine that does not require a person to be present in the excavation.
Special Precautionary Measures§
Fencing of a pit, excavation or slope§
Safety in Work on Bored Pile Drilling§
No person shall enter or be employed inside a bored pile hole.
Ascent and Descent§
Width of Trenches§
A trench that is required to be shored under these Regulations shall be of sufficient width to permit the installation of suitable shoring and the proper and safe execution of the work for which the trench was excavated.
Trenches in Sandy Soil§
Crossings over Trenches§
Loose or Projecting Material§
Inspection§
Work on a Slope§
Where work is being carried out on or near a slope in the course of which or as a result of which rocks or other materials may slide down, appropriate working methods and tools shall be used and adequate measures shall be taken to prevent harm to persons or property from rocks, stones or materials as aforesaid.
Stability of a Quarried Wall§
A construction operator is responsible for ensuring that the quarrying of a wall is planned and executed so that its stability is secured by means of a stable gradient or by taking other appropriate measures to achieve the same purpose.
Inspection of a quarried wall and removal of projecting or loose material§
The site manager shall inspect, each day before the commencement of work, the stability of the quarried wall, and shall record the results of the inspection in accordance with regulation 122; if projecting or loose material is found in the inspection, it shall be removed in a safe manner.
Prohibition on a Person's Presence§
No person shall be required to be present, to pass or to work in a place where that person is liable to be harmed by loose material or an unstable wall.
Chapter X: Demolition
Supervision by a Site Manager§
A construction operator is responsible for ensuring that demolition work is carried out under the direct management of a site manager with at least one year's experience in the demolition of structures.
Execution of Demolition§
(Repealed — תשפ״ו)
Safety Measures§
Warning§
Stoppage of work§
Chapter XI: Hot Bitumen
Suitability of Workers§
A construction operator is responsible for ensuring that work involving the use of hot bitumen is carried out under the direct supervision of an experienced worker and that all bitumen is heated by an experienced worker.
Place of Use§
Bitumen shall not be heated except at a distance of at least 6 metres from a place where flammable materials are present; if the conditions of the site do not permit the maintenance of such a distance, a partition of non-flammable material shall be installed to separate the flammable materials from the fire, with the distance between the fire and the flammable materials being not less than 2 metres.
Heating Container§
Prevention of Spread of Fire§
Adequate measures shall be taken to prevent the spread of fire during the heating of bitumen, as a result of accidental ignition or the effect of wind.
Extinguishing Means§
Containers§