Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work), 5778-2018

תקנות התכנון והבנייה (הקמת מכון בקרה ודרכי עבודתו), תשע"ח-2018

Published: 2018-06-04Consolidated Hebrew text as of 2026-02-15 · Last amended 2024-06-26
Premium
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More

This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.

Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.

The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.

This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.

Section B: Supervision

Supervision of the Institute's Work§
85.

The person in charge shall supervise and audit the activities of inspection institutes and inspectors, including, inter alia, in the following matters:

(1)the manner of the institute's activity, including professional inspection capabilities, the reliability of the inspection performed and the level of service provided;
(2)the inspection institute's compliance with the provisions of the Law and these Regulations, including the fulfilment of all conditions for the grant of the licence or conditions included in the licence, its compliance with the timetable prescribed in these Regulations and the qualifications of office holders in the institute, and the person in charge may require declarations from office holders in the inspection institute in that regard.
Inspectors of Inspection Institutes§
86.
(a)An inspector authorised by the Minister of Finance under section 158ae(b) of the Law shall act in accordance with the directions of the person in charge on the matters detailed in regulation 85.
(b)The inspector shall report to the person in charge on the findings found in the work of an inspection institute in the format directed by the person in charge.
Correction of Defects and Flaws§
87.
(a)The person in charge shall notify an inspection institute of defects and flaws found on the basis of reports submitted to him, on the basis of examinations conducted by him, or on the basis of findings discovered by an inspector.
(b)Upon receipt by an inspection institute of a notice as referred to in sub-regulation (a), it shall notify the person in charge, within a period directed by the person in charge, of its response to the contents of the notice, and if it acted to correct the defects and flaws as aforesaid, it shall detail in its response the steps it took.
(c)Without derogating from the powers of the person in charge, if the person in charge considers that the defects or flaws as aforesaid constitute a breach of a material condition among the conditions of the licence or a breach of a provision of law, whether by act or by omission, he shall act in accordance with the powers set out in regulations 14 and 15.

Chapter IX: Inspection Domains

Areas of Design Inspection and Construction Inspection§

88.
(a)Sample design inspection and sample construction inspection shall cover matters of building design within the following areas, if they are required in respect of that work:
(1)stability of the frame and foundation of the building;
(2)fire safety, evacuation and rescue;
(3)user safety from harm: from slipping, falling, collision or burning;
(4)waterproofing of parts of the building that come into contact with the ground or are located underground;
(5)sanitary installations;
(6)ventilation of the building;
(7)drainage for the prevention of flooding and soil pollution and the implementation of detention and infiltration;
(8)protection – shelter and protected space;
(9)protection of the structure and its occupants from hazardous materials;
(10)acoustics.
(b)Process inspection shall cover matters of building design in the areas set out in sub-regulation (a) and in the following areas, if they are required in respect of that work:
(1)radiation;
(2)asbestos;
(3)electrical safety;
(4)thermal insulation;
(5)accessibility.
(c)An inspection institute shall carry out design inspection and construction inspection in accordance with process and sample inspection specifications to be published by the person in charge on the website of the Planning Administration and based on the principle of risk assessment according to the type and use of the structure.
(d)Authorised inspectors in an inspection institute shall exercise their authority in accordance with the guidelines and instructions given and published by the Minister responsible for the relevant approving body or a senior employee of his Ministry's staff as referred to in section 158w(e) of the Law.
(e)Notwithstanding the provisions of sub-regulations (a) and (b), in the cases set out below the inspection institute shall carry out process inspection instead of sample inspection, in the types of permits or areas of design as directed by the person in charge by virtue of his authority under section 158ae1(d) of the Law:
(1)in the cases referred to in item 3 of the Sixth Schedule;
(2)for an existing building whose permit includes an addition;
(3)a portable structure manufactured according to a prototype; in this paragraph, "prototype" – a portable structure for which the required approvals under any law have been received, whose design conforms to the building design regulations and to the instructions of the approving bodies.

Design Inspection at the Engineer's Request§

89.

If the engineer considers that special circumstances exist that justify it, he may request an inspection institute to give its opinion within the framework of design inspection or construction inspection on matters of building design as referred to in regulation 88 that relate to user safety, the safety and stability of the building, provided that there is an effect on the environment or on public safety and health.

Authorised Health Inspector§

89a.
(a)Where a structure is subject to an obligation of inspection at an inspection institute, an authorised health inspector shall, before giving his approval, be subject to an obligation to approach the approving body for its response, in the types of buildings whose use or works are one of the following:
(1)(Repealed)
(2)(Repealed)
(3)a pharmacy and a medicine shop as defined in the Pharmacists Ordinance [New Version], 5741-1981;
(4)storage of medicines, medical equipment, cosmetics, food, cannabis;
(5)a medical laboratory as defined in regulation 1 of the Public Health (Medical Laboratories) Regulations, 5737-1977;
(6)an institute for a special device as defined in regulation 1 of the Public Health (Special Medical Devices) Regulations, 5754-1994, and an imaging institute;
(7)a hall or garden for celebrations and events;
(8)construction located in a protection zone as defined in the Public Health (Sanitary Conditions for Drinking Water Drilling) Regulations, 5755-1995;
(9)an oncology clinic, a dialysis clinic and a clinic in which minor or intermediate surgical procedures are performed as defined in the Public Health (Registration of Clinics) Regulations, 5747-1987;
(10)a family health station (mother and child health clinic);
(11)a shopping mall.
(12)a rehabilitative day care centre as defined in the Rehabilitative Day Care Centres Law, 5760-2000.
(b)Notwithstanding the provisions of sub-regulation (a), the authority vested in the Minister of Health as an approving body or in any of his Ministry's employees shall not be vested in an authorised health inspector, in the types of buildings subject to an obligation of inspection at an inspection institute whose use or works are one of the following:
(1)a nursing ward in a care home as defined in item 7.1g in Column A of the Schedule to the Business Licensing (Businesses Requiring a Licence) Order, 5773-2013, or in a protected housing home as defined in the Protected Housing Law, 5772-2012;
(2)a swimming pool intended for the general public for sports and recreation purposes and a swimming pool at a hospitality or accommodation site intended for the use of more than four accommodation units, as well as ritual immersion pools, public baths, a public current pool, a water park, water slides.
(3)an industrial structure for the manufacture, treatment, packaging and storage of food including beverages and raw materials, and an industrial structure for the manufacture of medicines, cosmetics or medical equipment.

Authorised Civil Defence Inspector§

89b.
(a)Where a structure is subject to an obligation of inspection at an inspection institute, an authorised civil defence inspector shall, before giving his approval, be subject to an obligation to approach the approving body for its response, in the types of buildings whose use or works are one of the following:
(1)a clinic in respect of which it was decided at the permit information stage that it requires a dedicated protected space in health institutions under the Civil Defence (Specifications for the Construction of Shelters) Regulations, 5750-1990;
(2)structures comprising mixed uses including uses of education, welfare or health.
(3)educational buildings.
(b)Notwithstanding the provisions of sub-regulation (a), the authority vested in the approving body shall not be vested in an authorised civil defence inspector, in the types of buildings subject to an obligation of inspection at an inspection institute whose use or works are one of the following:
(1)(Repealed)
(2)welfare institutions.
(c)Notwithstanding the provisions of sub-regulations (a) and (b), the authority vested in the approving body to grant an exemption from the construction of a protected space or shelter shall not be vested in an authorised civil defence inspector, in the types of buildings, uses or works subject to an obligation of inspection at an inspection institute under these Regulations.

Authorised Fire Safety Inspector§

89c.
(a)Where a structure is subject to an obligation of inspection at an inspection institute, an authorised fire safety inspector shall, before giving his approval, be subject to an obligation to approach the approving body for its response, in a permit that includes the erection of a building using a new building method as defined in the Building Licensing Regulations, that has been lawfully approved.
(b)Notwithstanding the provisions of sub-regulation (a), the authority vested in the National Fire and Rescue Authority as an approving body or in a person holding a position therein shall not be vested in an authorised fire safety inspector in the types of buildings subject to an obligation of inspection at an inspection institute whose use or works are one of the following:
(1)a structure whose height exceeds 60 metres;
(2)a hotel as defined in the Permit Application Regulations containing at least 200 rooms in a single structure;
(3)a hostel as defined in the Supervision of Hostels Law, 5725-1965, for the residence of persons with disabilities as defined in the Equal Rights for Persons with Disabilities Law, 5758-1998;
(4)care homes, including nursing wards;
(5)a structure classified as high risk in a fire risk assessment report under sub-item 3.4.11.17(c)(5) or sub-item 3.4.11.18(a) of the Second Schedule, Part 3, Chapter IV, Section J of the Permit Application Regulations;
(6)a building permit application that includes a natural gas system;
(7)a building permit application in which a safety survey is required under item 3.9.16.3 of the Second Schedule of the Permit Application Regulations;
(8)a high-rise or multi-storey building that includes an atrium; in this paragraph, "atrium" – a covered void connecting four or more floors, and not serving any of the following: a staircase, a lift shaft, an escalator, a shaft;
(9)a stadium, a sports facility and any other place of assembly that is requested to be defined as a smoke-protected place of assembly as defined in item 3.9.1.1 of Part 3 of the Second Schedule of the Permit Application Regulations;
(10)a shopping mall;
(11)an addition to an existing structure operating with a fire risk array subject to regulations under the Business Licensing Law, 5728-1968, or the National Fire and Rescue Authority Law, 5772-2012, that has received approval from the Fire and Rescue Authority or is in inspection proceedings conducted by it.

Authorised Environmental Protection Inspector§

89d.

The authority vested in the Minister for Environmental Protection as an approving body or in any of her Ministry's employees shall not be vested in an authorised environmental inspector, in the types of buildings, uses or works subject to an obligation of inspection at an inspection institute under these Regulations.

Process of Obtaining a Response from an Approving Body§

89e.
(a)Where an authorised inspector is required to obtain a response from an approving body, the authorised inspector shall approach the approving body within one day and shall attach to his approach a main plan and any material or information required under the approving body's instructions.
(b)The approving body shall provide its response to the authorised inspector within fifteen days of the date of the approach, and in respect of educational buildings that are not part of a structure comprising mixed uses – within 21 days of the date of the approach, and the authorised inspector shall forward it to the applicant in the interim report as referred to in regulation 42(c).
(c)If the approving body has required in its response that the application be amended, the application drafter shall submit an amended application to the inspection institute, one or more times, provided that the last amended application is submitted to the inspection institute and the inspection institute forwards it to the approving body no later than ten days before the end of the design inspection period; the approving body shall provide its response within five days of the date of the approach.
(d)If the approving body has not given its response by the date prescribed as referred to in sub-regulation (b) or (c), the authorised inspector shall exercise his authority in accordance with the guidelines and instructions of the approving body and in accordance with the information provided by the approving body as referred to in section 158w(f) of the Law.

Authorised Inspectors§

90.
(a)If the provisions of section 158o1 of the Law are fulfilled and there is no authorised inspector in the inspection institute in respect of an approving body, the inspection institute shall not carry out design inspection and construction inspection in respect of the authority vested in that approving body.
(b)If it is prescribed in these Regulations that the authority of an approving body is not vested in an authorised inspector but in an approving body, the inspection institute shall not carry out design inspection and construction inspection in respect of the authority vested in that approving body.

Chapter IX-A: Licensing Procedure by means of a Permit Authorised Person

Provisions concerning the licensing procedure by means of a permit authorised person under Chapter V-D of the Law§

90a.

In design inspection and construction inspection in respect of a licensing procedure by means of a permit authorised person as referred to in Chapter V-D of the Law, these Regulations shall be read with the following modifications:

(1)Everywhere, except in regulation 60(c), instead of "the licensing authority" or "the engineer" read "the permit authorised person", and the necessary grammatical adjustments shall be made accordingly;
(2)The provision of regulation 39(1) shall not apply;
(3)In regulation 48(12), instead of "the engineer's assessment as referred to in regulation 56 of the Building Licensing Regulations" read "unless otherwise determined in the permit information as defined in section 158au of the Law that was provided";
(4)In regulation 60(c), after "to the committee's engineer" read "and to the permit authorised person";
(5)In item 12 of the First Schedule, in the preamble, the words "at the time of delivery of the permit information" – shall be deleted.

Chapter X: Commencement and Transitional Provision

Commencement and application§

91.
(a)In this regulation –

"multi-storey building" and "dense construction" – as defined in the Principal Regulations;

"public building" – a building used for public purposes for education, culture, religion, welfare and social services, health, sport, excluding institutions of higher education, hospitals and a residence as defined in the Supervision of Residences Law, 5725-1965, for persons with disabilities as defined in the Equal Rights for Persons with Disabilities Law, 5758-1998.

(b)The obligation to undergo inspection at an inspection institute shall apply to a permit application submitted to the local committee on or after 25 Sivan 5784 (1 July 2024) whose date of approval by the licensing authority is on or after the date of publication of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5784-2024, and which includes any of the following:
(1)Erection of a building in which one or more of the uses listed below are used, provided that the total area of the building exceeds that prescribed in regulation 18(a)(2) of the Building Licensing Regulations as defined in the Principal Regulations:
(a)a new residential building up to a height of 42 metres;
(b)a public building, offices, commerce excluding a shopping centre, that are not in a building that constitutes a multi-storey building;
(2)Construction of part of a building whose overall construction is subject to the inspection obligation of an inspection institute;
(3)Execution of additions or alterations to a building permit in respect of which inspection by an inspection institute has commenced but in respect of which a completion certificate has not yet been issued, provided that the building including the additions or alterations is of a type of building in respect of which the inspection obligation of an inspection institute applies.
(c)During the period from 1 Tevet 5785 (1 January 2025), in addition to that stated in sub-regulation (b), the inspection obligation at an inspection institute shall also apply to the erection of a building in which one or more of the following uses are present:
(1)Commerce, including a shopping centre, and offices in a building where the height difference between the level of the determining entrance to the building and the level of the entrance to the highest storey intended for occupancy, access to which is through a shared stairwell, does not exceed 42 metres;
(2)A public building also intended for institutions of higher education that is not in a building that constitutes a multi-storey building;
(3)A storage building that is not in a building that constitutes a multi-storey building, and excluding –
(a)a warehouse that includes a large fire load as defined in regulation 3.1.1.1 of the Second Schedule to the Permit Application Regulations;
(b)a warehouse intended to contain a hazardous substance that requires a poisons permit under the Hazardous Substances Law, 5753-1993.
(d)The commencement of regulation 89b(a) as formulated in the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5784-2024, is 1 Tevet 5785 (1 January 2025) with respect to permit applications approved by the licensing authority on or after that date.
(e)Permit applications submitted to the licensing authority in respect of the types of structures, works and uses set out in the Sixth Schedule from 12 Tevet 5786 (1 January 2026) shall not be subject to the inspection obligation by means of an inspection institute.
(f)The inspection obligation at an inspection institute pursuant to the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5786-2026, shall apply to a permit application submitted to the local committee on or after 12 Tevet 5786 (1 January 2026), whose date of approval by the licensing authority or the national licensing authority or by means of a permit authorised person is on or after the date of publication of these Regulations.
92.§

(Repealed — תשפ״ו)

Temporary provision§

93.
(a)Notwithstanding the provisions of regulation 45(b) concerning the transfer of design annexes to the licensing authority, during the period from the date of commencement of these Regulations until 6 Iyar 5780 (30 April 2020), the application drafter shall transfer to the licensing authority the design annexes sent to him by the inspection institute as referred to in regulation 45(b), and the obligation shall not apply to the inspection institute to attach the design annexes to the notification to the licensing authority as referred to in regulation 45(a).
(b)Notwithstanding the provisions of regulation 88(a) and (b), during the period from the date of commencement of these Regulations until 26 Nisan 5779 (1 May 2019), an inspection institute shall not carry out inspection as referred to in those sub-regulations in the fields listed below, and the person in charge may shorten the said period with respect to the said fields, in whole or in part:
(1)acoustics;
(2)radiation;
(3)asbestos;
(4)electrical safety.
(c)Notwithstanding the provisions of regulation 89b(a)(1), the authority vested in an approving body shall not be vested in an authorised civil defence inspector, in the type of buildings subject to the inspection obligation of an inspection institute where the use or works therein are one of those listed below and whose date of approval of the permit application by the licensing authority falls within the period from the date of publication of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5784-2024, until 30 Kislev 5785 (31 December 2024):
(1)clinics.
(d)Notwithstanding the provisions of regulation 89b(a)(2), where a building is subject to the inspection obligation of an inspection institute, an authorised civil defence inspector shall be subject, prior to granting his approval, to the obligation to obtain the response of the approving body, in the type of buildings where the use or works therein are one of those listed below and whose date of approval of the permit application by the licensing authority falls within the period from the date of publication of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5784-2024, until 30 Kislev 5785 (31 December 2024):
(1)buildings that include a mix of uses that do not include the uses of education; welfare; health.
(e)Notwithstanding the provisions of sub-regulation 89a(a), where a building is subject to the inspection obligation of an inspection institute, an authorised health inspector shall be subject, prior to granting his approval, during a period of four years from the date of commencement of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5786-2026, to the obligation to obtain the response of the approving body, in the type of buildings where the use or works therein are one of the following:
(1)a supermarket that includes food processing and a butcher's shop;
(2)a restaurant and any place intended to be used for the preparation of food, including in institutions and excluding for personal use.
(f)Notwithstanding the provisions of sub-regulation 89b(a), where a multi-storey building whose height exceeds 42 metres is subject to the inspection obligation of an inspection institute, an authorised civil defence inspector shall be subject, prior to granting his approval, during a period of four years from the date of commencement of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5786-2025, to the obligation to obtain the response of the approving body.
(g)Notwithstanding the provisions of sub-regulation 89b(a)(1), the authority vested in an approving body shall not be vested in an authorised civil defence inspector during a period of four years from the date of commencement of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5786-2026.
(h)In addition to that stated in sub-regulation 89c(b), during a period of four years from the date of commencement of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5786-2026, the authority as an approving body in respect of a building whose height is above 42 metres up to 60 metres that is subject to the inspection obligation of an inspection institute shall not be vested in an authorised fire safety inspector but only in the National Fire and Rescue Authority or in a person performing a function therein.
(i)During the period from the date of publication of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5786-2026, until 26 Tevet 5790 (1 January 2030), it shall be deemed as if at the end of item 2 of the Fifth Schedule the following were stated:
Temporary provision
Column A – Type of work and useColumn B – Details of construction area bColumn C – Design stage – payment in new shekels per square metreColumn D – Construction stage – payment in new shekels per square metre
New dense construction, for residential purposes only, in a building that is not a high-rise building or a multi-storey buildingConstruction area up to 1,000 inclusive7,632, plus 8.18 for each square metre above 30014,173, plus 14.99 for each square metre above 300
Construction area above 1,000 up to 2,000 inclusive13,355, plus 4.09 for each square metre above 1,00024,666, plus 6.81 for each square metre above 1,000
Construction area above 2,00017,443, plus 3.41 for each square metre above 2,00031,480, plus 5.45 for each square metre above 2,000
New dense construction for residential purposes only, in a high-rise building that is not a multi-storey buildingConstruction area up to 2,000 inclusive14,309, plus 4.09 for each square metre above 1,00026,574, plus 8.18 for each square metre above 1,000
Construction area above 2,000 up to 6,000 inclusive18,397, plus 3.41 for each square metre above 2,00034,751, plus 6.13 for each square metre above 2,000
Construction area above 6,00032,025, plus 0.68 for each square metre above 6,00059,280, plus 1.36 for each square metre above 6,000
New dense construction for residential purposes only, in a multi-storey building up to 42 metresConstruction area up to 9,000 inclusive39,512, plus 1.94 for each square metre above 6,00060,127, plus 1.32 for each square metre above 6,000
Construction area above 9,000 up to 15,000 inclusive45,326, plus 2.25 for each square metre above 9,00064,091, plus 4.20 for each square metre above 9,000
Construction area above 15,00058,856, plus 1.14 for each square metre above 15,00089,289, plus 1.61 for each square metre above 15,000
New dense construction for residential purposes only, in a multi-storey building 42 metres and aboveConstruction area up to 15,000 inclusive61,050, plus 0.66 for each square metre above 10,00073,260, plus 3.17 for each square metre above 10,000
Construction area above 15,000 up to 20,000 inclusive64,350, plus 1.01 for each square metre above 15,00089,100, plus 0.81 for each square metre above 15,000
Construction area above 20,000 up to 25,000 inclusive69,410, plus 0.89 for each square metre above 20,00093,170, plus 1.99 for each square metre above 20,000
Construction area above 25,000 up to 30,000 inclusive73,873, plus 0.29 for each square metre above 25,000103,101, plus 1.42 for each square metre above 25,000
Construction area above 30,00075,330, plus 0.22 for each square metre above 30,000110,220, plus 0.92 for each square metre above 30,000
Public building, that is not a high-rise building or a multi-storey buildingConstruction area up to 300 inclusive13,20018,150
Construction area above 300 up to 500 inclusive24,77833,037
Construction area above 500 up to 1,000 inclusive24,778, plus 13.88 for each square metre above 50033,037, plus 21.80 for each square metre above 500
Construction area above 1,000 up to 2,000 inclusive31,715, plus 2.97 for each square metre above 1,00043,939, plus 3.30 for each square metre above 1,000
Construction area above 2,000 up to 3,000 inclusive34,650, plus 3.96 for each square metre above 2,00047,190, plus 6.93 for each square metre above 2,000
Construction area above 3,000 up to 4,000 inclusive38,610, plus 1.49 for each square metre above 3,00054,120, plus 0.88 for each square metre above 3,000
Construction area above 4,000 up to 5,000 inclusive40,095, plus 2.26 for each square metre above 4,00055,000, plus 2.20 for each square metre above 4,000
Construction area above 5,000 up to 6,000 inclusive42,350, plus 2.86 for each square metre above 5,00057,200, plus 2.20 for each square metre above 5,000
Construction area above 6,000 up to 8,000 inclusive45,210, plus 1.46 for each square metre above 6,00059,400, plus 2.09 for each square metre above 6,000
Construction area above 8,00048,125, plus 1.38 for each square metre above 8,00063,580, plus 1.10 for each square metre above 8,000
Public building, in a high-rise building that is not a multi-storey buildingConstruction area 1,000 up to 4,000 inclusive36,010, plus 2.46 for each square metre above 1,00052,859, plus 4.97 for each square metre above 1,000
Construction area above 4,000 up to 5,000 inclusive43,389, plus 2.43 for each square metre above 4,00067,725, plus 5.95 for each square metre above 4,000
Construction area above 5,00046,090, plus 2.20 for each square metre above 5,00072,600, plus 2.52 for each square metre above 5,000
Public building, in a multi-storey building above 29 metresConstruction area up to 6,000 inclusive52,800, plus 1.57 for each square metre above 3,00064,020, plus 4.32 for each square metre above 3,000
Construction area above 6,000 up to 9,000 inclusive57,510, plus 1.7 for each square metre above 6,00076,980, plus 2.34 for each square metre above 6,000
Construction area above 9,000 up to 12,000 inclusive62,820, plus 0.59 for each square metre above 9,00084,000, plus 2.93 for each square metre above 9,000
Construction area above 12,000 up to 15,000 inclusive64,586, plus 0.80 for each square metre above 12,00092,777, plus 2.68 for each square metre above 12,000
Construction area above 15,000 up to 17,000 inclusive66,990, plus 1.66 for each square metre above 15,000100,815, plus 0.91 for each square metre above 15,000
Construction area above 17,00070,302, plus 0.68 for each square metre above 17,000102,642, plus 0.68 for each square metre above 17,000
Commerce building, that is not a high-rise building or a multi-storey buildingConstruction area up to 1,000 inclusive9,297 plus 18.20 for each square metre above 30027,857 plus 18.73 for each square metre above 300
Construction area above 1,000 up to 3,000 inclusive22,134, plus 6.11 for each square metre above 1,00039,975, plus 6.44 for each square metre above 1,000
Construction area above 3,000 up to 5,000 inclusive34,358, plus 2.42 for each square metre above 3,00052,859, plus 3.16 for each square metre above 3,000
Construction area above 5,00039,203, plus 2.42 for each square metre above 5,00057,940, plus 2.00 for each square metre above 5,000
Commerce building, in a high-rise building that is not a multi-storey buildingConstruction area up to 4,000 inclusive30,063, plus 2.32 for each square metre above 1,00040,635, plus 6.28 for each square metre above 1,000
Construction area above 4,000 up to 5,000 inclusive37,332, plus 7.93 for each square metre above 4,00056,824, plus 1.65 for each square metre above 4,000
Construction area above 5,00045,922, plus 0.92 for each square metre above 5,00058,476, plus 2.63 for each square metre above 5,000
Commerce building, in a multi-storey building up to 42 metresConstruction area up to 9,000 inclusive50,216, plus 1.66 for each square metre above 6,00065,743, plus 1.66 for each square metre above 6,000
Construction area 9,000 up to 12,000 inclusive55,171, plus 1.10 for each square metre above 9,00070,699, plus 3.08 for each square metre above 9,000
Construction area above 12,00058,475, plus 0.99 for each square metre above 12,00079,949, plus 3.05 for each square metre above 12,000
Commerce building, in a multi-storey building 42 metres and aboveConstruction area up to 15,000 inclusive59,070, plus 0.79 for each square metre above 10,00079,530, plus 2.44 for each square metre above 10,000
Construction area above 15,000 up to 20,000 inclusive63,030, plus 1.28 for each square metre above 15,00091,740, plus 1.47 for each square metre above 15,000
Construction area above 20,000 up to 25,000 inclusive69,410, plus 0.78 for each square metre above 20,00099,110, plus 1.76 for each square metre above 20,000
Construction area above 25,000 up to 30,000 inclusive73,307, plus 0.49 for each square metre above 25,000107,910, plus 1.06 for each square metre above 25,000
Construction area above 30,00075,750, plus 0.51 for each metre above 30,000113,220, plus 0.76 for each metre above 30,000
Office building that is not a high-rise building or a multi-storey buildingConstruction area up to 1,000 inclusive11,449, plus 19.99 for each square metre above 30026,420, plus 20.32 for each square metre above 300
Construction area above 1,000 up to 3,000 inclusive25,438, plus 6.29 for each square metre above 1,00040,635, plus 6.10 for each square metre above 1,000
Construction area above 3,000 up to 5,000 inclusive37,992, plus 6.95 for each square metre above 3,00052,859, plus 6.43 for each square metre above 3,000
Construction area above 5,00051,868, plus 0.74 for each square metre above 5,00065,743, plus 2.97 for each square metre above 5,000
Office building, in a high-rise building that is not a multi-storey buildingConstruction area up to 4,000 inclusive31,385, plus 4.51 for each square metre above 1,00042,287, plus 5.73 for each square metre above 1,000
Construction area above 4,000 up to 5,000 inclusive44,930, plus 6.94 for each square metre above 4,00059,466, plus 6.28 for each square metre above 4,000
Construction area above 5,00051,868, plus 1.28 for each square metre above 5,00065,743, plus 2.09 for each square metre above 5,000
Office building, in a multi-storey building up to 42 metresConstruction area up to 9,000 inclusive53,520, plus 1.54 for each square metre above 6,00070,699, plus 1.54 for each square metre above 6,000
Construction area 9,000 up to 12,000 inclusive58,145, plus 0.77 for each square metre above 9,00075,324, plus 2.97 for each square metre above 9,000
Construction area above 12,00060,457, plus 1.32 for each square metre above 12,00084,244, plus 2.44 for each square metre above 12,000
Office building or knowledge-intensive industrial building, in a multi-storey building 42 metres and aboveConstruction area up to 15,000 inclusive59,070, plus 1.98 for each square metre above 10,00083,490, plus 2.05 for each square metre above 10,000
Construction area above 15,000 up to 20,000 inclusive68,970, plus 0.75 for each square metre above 15,00093,720, plus 1.47 for each square metre above 15,000
Construction area above 20,000 up to 25,000 inclusive72,710, plus 0.78 for each square metre above 20,000101,090, plus 1.76 for each square metre above 20,000
Construction area above 25,000 up to 30,000 inclusive76,607, plus 0.60 for each square metre above 25,000109,890, plus 0.95 for each square metre above 25,000
Construction area above 30,00079,590, plus 0.52 for each square metre above 30,000114,660, plus 0.88 for each square metre above 30,000
Storage building that is not a high-rise building or a multi-storey buildingConstruction area up to 1,000 inclusive9,580, plus 18.88 for each square metre above 30028,081, plus 18.88 for each square metre above 300
Construction area above 1,000 up to 2,000 inclusive22,770, plus 7.26 for each square metre above 1,00041,250, plus 3.30 for each square metre above 1,000
Construction area above 2,000 up to 3,000 inclusive30,030, plus 5.94 for each square metre above 2,00044,550, plus 8.91 for each square metre above 2,000
Construction area above 3,000 up to 5,000 inclusive35,970, plus 2.20 for each square metre above 3,00053,460, plus 3.08 for each square metre above 3,000
Construction area above 5,000 up to 7,000 inclusive40,370, plus 2.59 for each square metre above 5,00059,620, plus 3.69 for each square metre above 5,000
Construction area above 7,00045,540, plus 2.71 for each square metre above 7,00066,990, plus 2.57 for each square metre above 7,000
Storage building, in a high-rise building that is not a multi-storey buildingConstruction area 1,000 up to 4,00030,063, plus 3.20 for each square metre above 1,00043,278, plus 6.28 for each square metre above 1,000
Construction area above 4,000 up to 5,000 inclusive39,644, plus 7.27 for each square metre above 4,00062,109, plus 5.29 for each square metre above 4,000
Construction area above 5,00046,912, plus 1.21 for each square metre above 5,00067,395, plus 0.96 for each square metre above 5,000
Storage building, in a multi-storey building above 29 metresConstruction area up to 6,000 inclusive40,260, plus 3.92 for each square metre above 3,00064,680, plus 2.02 for each square metre above 3,000
Construction area above 6,000 up to 8,000 inclusive52,030, plus 2.20 for each square metre above 6,00070,730, plus 0.28 for each square metre above 6,000
Construction area above 8,000 up to 12,000 inclusive56,430 plus 1.55 for each square metre above 8,00071,280, plus 2.51 for each square metre above 8,000
Construction area above 12,00062,610, plus 0.90 for each square metre above 12,00081,300, plus 2.40 for each square metre above 12,000
Industrial building that is not a high-rise building or a multi-storey buildingConstruction area up to 1,000 inclusive22,11039,930
Construction area above 1,000 up to 2,000 inclusive22,110, plus 5.28 for each square metre above 1,00039,930, plus 2.97 for each square metre above 1,000
Construction area above 2,000 up to 3,000 inclusive27,390, plus 5.61 for each square metre above 2,00042,900, plus 9.90 for each square metre above 2,000
Construction area above 3,000 up to 6,000 inclusive33,000, plus 2.09 for each square metre above 3,00052,800, plus 3.52 for each square metre above 3,000
Construction area above 6,00039,270, plus 2.81 for each square metre above 6,00063,360, plus 2.53 for each square metre above 6,000
Industrial building, in a high-rise building that is not a multi-storey buildingConstruction area up to 3,00028,875, plus 2.89 for each square metre above 1,00037,455, plus 7.84 for each square metre above 1,000
Construction area above 3,000 up to 6,000 inclusive34,650, plus 4.07 for each square metre above 3,00053,130, plus 4.18 for each square metre above 3,000
Construction area above 6,00046,860 plus 1.73 for each square metre above 6,00065,670, plus 1.65 for each square metre above 6,000
Industrial building, in a multi-storey building above 29 metresConstruction area up to 6,000 inclusive36,894, plus 4.09 for each square metre above 3,00053,346, plus 4.11 for each square metre above 3,000
Construction area above 6,000 up to 9,000 inclusive49,170, plus 2.42 for each square metre above 6,00065,670, plus 1.87 for each square metre above 6,000
Construction area above 9,000 up to 12,000 inclusive56,430, plus 1.54 for each square metre above 9,00071,280, plus 3.08 for each square metre above 9,000
Construction area above 12,00061,050, plus 0.83 for each square metre above 12,00080,520, plus 2.53 for each square metre above 12,000
Hotels, guest houses, boarding schools, that are not a high-rise building or a multi-storey buildingConstruction area up to 1,000 inclusive33,33043,560
Construction area above 1,000 up to 3,000 inclusive33,330 plus 4.46 for each square metre above 1,00043,560, plus 4.62 for each square metre above 1,000
Construction area above 3,000 up to 7,00042,240 plus 2.39 for each square metre above 3,00052,800, plus 4.46 for each square metre above 3,000
Construction area above 7,00051,810 plus 1.72 for each square metre above 7,00070,620, plus 3.17 for each square metre above 7,000
Hotels, guest houses, boarding schools, in a high-rise building that is not a multi-storey buildingConstruction area up to 3,000 inclusive40,260, plus 2.64 for each square metre above 1,00052,140, plus 2.64 for each square metre above 1,000
Construction area above 3,000 up to 5,000 inclusive45,540, plus 2.48 for each square metre above 3,00057,420, plus 7.43 for each square metre above 3,000
Construction area above 5,000 up to 7,000 inclusive50,490, plus 3.30 for each square metre above 5,00072,270, plus 1.82 for each square metre above 5,000
Construction area above 7,000 up to 9,000 inclusive57,090, plus 1.32 for each square metre above 7,00075,900, plus 1.82 for each square metre above 7,000
Construction area above 9,00059,730, plus 0.88 for each square metre above 9,00077,880, plus 0.95 for each square metre above 9,000
Hotels, guest houses, boarding schools, in a multi-storey building up to 42 metresConstruction area up to 6,000 inclusive48,840, plus 3.41 for each square metre above 3,00073,260, plus 2.86 for each square metre above 3,000
Construction area above 6,000 up to 9,000 inclusive59,070, plus 1.43 for each square metre above 6,00081,840, plus 1.54 for each square metre above 6,000
Construction area above 9,000 up to 12,000 inclusive63,360, plus 1.10 for each square metre above 9,00086,460, plus 2.42 for each square metre above 9,000
Construction area above 12,000 up to 15,000 inclusive66,660, plus 1.26 for each square metre above 12,00093,720, plus 2.45 for each square metre above 12,000
Construction area above 15,00070,431, plus 0.75 for each square metre above 15,000101,074, plus 0.94 for each square metre above 15,000
Hotels, guest houses, boarding schools, in a multi-storey building 42 metres and aboveConstruction area up to 15,000 inclusive63,360, plus 1.42 for each square metre above 9,00092,400, plus 1.46 for each square metre above 9,000
Construction area above 15,000 up to 20,000 inclusive71,883, plus 0.98 for each square metre above 15,000101,181, plus 1.41 for each square metre above 15,000
Construction area above 20,000 up to 25,000 inclusive76,780, plus 0.69 for each square metre above 20,000108,240, plus 1.55 for each square metre above 20,000
Construction area above 25,000 up to 30,000 inclusive80,237, plus 0.43 for each square metre above 25,000115,971, plus 1.03 for each square metre above 25,000
Construction area above 30,00082,410, plus 0.77 for each square metre above 30,000121,140, plus 0.82 for each square metre above 30,000

First periodic review§

94.

The first periodic review of the Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work) (Amendment), 5786-2026, pursuant to section 24 of the Principles of Regulation Law, 5782-2021, shall be conducted at the end of five years from the date of their commencement.