Israeli Legislation.com

Planning and Building Regulations (Establishment of an Inspection Institute and Its Methods of Work), 5778-2018

תקנות התכנון והבנייה (הקמת מכון בקרה ודרכי עבודתו), תשע"ח-2018

Published: 2018-06-04Consolidated Hebrew text as of 2026-02-15 · Last amended 2024-06-26
Premium
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More

This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.

Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.

The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.

This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.

Section B: Design Inspection

Design Inspection§
38.

An inspection institute shall conduct design inspection on the subjects and matters detailed in Chapter IX, except in areas that are not within the competence of an inspection institute as referred to in regulation 90.

39.§

The application drafter shall prepare an application for design inspection and shall submit it to the inspection institute online, together with all of the following:

(1)the decision of the licensing authority that the permit application meets the conditions of the spatial inspection as referred to in regulation 42 of the Building Licensing Regulations;
(2)the permit application file, including a main plan and a development plan conforming to the approving body's approval as referred to in paragraph (8);
(3)the design annexes required under the First Schedule, unless it is stated in the permit information that one or more of the design annexes are not required;
(4)a copy of the notice of appointment of sub-drafters;
(5)a declaration by the application drafter or the sub-drafters, as the case may be, regarding the conformity of the design annexes and any other document or annex prepared by them and submitted to the inspection institute, with the main plan and the decision of the licensing authority or the approving body's approval, if required;
(6)permit information provided under the Building Licensing Regulations, including detailed information provided under regulation 22 of those Regulations, if any;
(7)the documents detailed in the permit information file and in the decision of the licensing authority that are to be submitted to the inspection institute;
(8)the approval of an approving body listed in section 158u of the Law, if such an approving body's approval is required in respect of the permit application and the authority of the approving body in respect of that building or work is not vested in the authorised inspector of the inspection institute, or if there is no authorised inspector in the inspection institute in respect of that approving body.
Agreement for the Provision of Design Inspection Services§
40.

Upon submission of an application for design inspection to the inspection institute, the applicant shall enter into an agreement with the inspection institute for the provision of design inspection services, and shall pay the fee for design inspection of the application under Chapter VII and the Fifth Schedule.

Agreement for the Provision of Design Inspection Services for Partial Construction§
40a.

In addition to the provisions of regulation 40, for design inspection in the construction of part of a building whose overall construction is subject to the obligation of inspection by an inspection institute, the fee shall be calculated according to the total construction area of the structure intended to be built.

Agreement for the Provision of Design Inspection Services for Additions or Alterations§
40b.

In addition to the provisions of regulation 40, for design inspection for the execution of additions or alterations under a building permit in respect of which inspection by an inspection institute applies but in respect of which a completion certificate has not yet been issued, provided that the building incorporating the additions or alterations is of a type in respect of which the obligation of inspection by an inspection institute applies, the fee shall be calculated according to the construction area added to the areas previously approved at the inspection institute.

Receipt of an Application for Design Inspection at an Inspection Institute§
41.
(a)Where the applicant for design inspection has paid the payment to the inspection institute, the inspection institute shall verify, within five days, that all the documents and attachments required under regulation 39 have been submitted; upon submission of all the required documents and attachments as aforesaid, the application shall be received.
(b)Where the inspection institute finds that the application for design inspection submitted to it does not include all the documents and attachments required under regulation 39, it shall send to the author of the application for design inspection and to the applicant a notice setting out the missing particulars and attachments, and the applicant shall be entitled to notify the inspection institute of the termination of its engagement therewith and to receive a refund of the fee paid as referred to in regulation 76(4).
(c)Where the inspection institute has not given notice of its decision within five days of the date of submission of the application for design inspection, the application shall be deemed to have been received.
Examination of the Application for Design Inspection§
42.
(a)The inspection institute shall carry out design inspection within 51 days of the date of receipt of the application for design inspection.
(b)An inspection institute may, within the design inspection period, require documents, explanations and clarifications from application authors as needed for the inspection, including design annexes detailed in item 12 of the First Schedule even if they were not required pursuant to that item.
(c)An inspection institute shall submit to the application author an interim report in a format directed by the person in charge, consolidating the inspection findings it has carried out including the opinions of the authorised inspectors, if required in respect of the work or building that is the subject of the application, no later than twenty days from the date of receipt of the application for design inspection, and the application author shall be entitled to submit an amended application to the inspection institute, one or more times, provided that the last amended application is submitted to the inspection institute no later than five days before the end of the design inspection period.
(d)Notwithstanding the provisions of sub-regulation (c), where it is determined in these Regulations that in respect of the work or building that is the subject of the permit application the response of the approving body is required under section 158w(f) of the Law, the inspection institute shall act in accordance with regulation 89e.
(e)Notwithstanding the provisions of sub-regulations (c) and (d), the design inspection manager may permit the application author to submit amendments to the application at any time, provided that the amended application is submitted within the design inspection period and before the dispatch of the notice and the design inspection summary opinion to the licensing authority, as referred to in regulation 45.
(f)Nothing in sub-regulations (c) and (d) shall derogate from the authority of an inspection institute to detail findings in a summary opinion under regulation 45, even if they were not included in the interim report.
Obtaining a Response from an Approving Body§
43.
(a)Where it is determined in these Regulations that in respect of the work or building that is the subject of the permit application the response of the approving body is required, section 158w(f) of the Law and the provisions of these Regulations shall apply.
(b)The count of days referred to in these Regulations is included within the count of days referred to in regulation 42(a) or 44(a), as the case may be.
(c)Notwithstanding the provisions of sub-regulation (b), in a case where an authorised civil defence inspector is required to obtain the response of the approving body in respect of educational buildings that are not part of a structure incorporating mixed uses as referred to in regulation 89e(b), 6 days shall be added to the periods enumerated in sub-regulations (a) and (c) of regulation 42.
Extension of the Inspection Period§
44.
(a)Notwithstanding the provisions of regulation 42(a), in the following cases design inspection shall be carried out within 60 days of the date of receipt of the application for design inspection:
(1)where the inspection relates to a complex structure as detailed in the Fourth Schedule;
(2)where it is determined in these Regulations that in respect of the work or building that is the subject of the permit application the response of two or more approving bodies is required.
(b)In an application as referred to in sub-regulation (a), the inspection institute shall submit to the application author an interim report as referred to in regulation 42(c) no later than the end of 30 days from the commencement of the inspection, and the application author shall be entitled to submit an amended application to the inspection institute, one or more times, provided that the last amended application is submitted to the inspection institute no later than ten days before the end of the design inspection period.
(c)Regulation 42(e) and (f) shall apply to applications as referred to in sub-regulation (a).
Summary Opinion of the Design Inspection§
45.
(a)Upon completion of the design inspection, if it is found to be in order, the design inspection manager shall notify the licensing authority that design inspection has been carried out and found to be in order; the design annexes shall be attached to the notice in a manner directed by the person in charge pursuant to the person in charge's authority under section 158ae1(c) of the Law.
(b)The design inspection manager shall transmit the results of the design inspection to the application author and to the applicant, together with the design annexes and a summary opinion of the design inspection setting out the results of the design inspection, which shall include the conclusions and guidelines of the authorised inspectors who examined the application, if they were required, and which shall indicate whether the design inspection was found to be in order and whether design alterations were made to the application documents; where the design inspection is found not to be in order, the report shall detail all the design findings found not to be in order and the corrections required.
(c)The design inspection manager shall include in the summary opinion recommendations to the licensing authority in the area of building design on the following matters, if there are such recommendations:
(1)the imposition of conditions in the permit, conditions for the granting of commencement of works approval, conditions during the course of execution of the work that is the subject of the permit, or conditions for the granting of a completion certificate;
(2)additional attachments and documents which it is recommended that the permit specify are to be transmitted to the inspection institute before the commencement of execution of the works, during the course thereof, or before submission of an application for a completion certificate, without derogating from the provisions of regulations 48 and 63(6).
Failure to Meet Deadlines§
46.

Where the deadline for carrying out design inspection as referred to in regulations 42 and 44, as the case may be, has passed and a summary opinion as referred to in regulation 45 has not been given, the applicant shall be entitled to notify the inspection institute within 5 days of the date on which the deadline for submission of the summary opinion has passed, and before the summary opinion as aforesaid has been given, of the termination of its engagement therewith, and to receive a refund of the fee paid as referred to in regulation 76(6).

Section C: Construction Inspection

Construction Inspection§
47.

Where an inspection institute has carried out design inspection, construction inspection shall be carried out in respect of the same permit application on the matters and subjects detailed in Chapter IX, except in areas that are not within the authority of an inspection institute as referred to in regulation 90.

Application for Construction Inspection§
48.

The person responsible for supervision of execution shall prepare an application for construction inspection and submit it to the inspection institute online, specifying the following particulars and documents:

(1)an electronic file of the permit;
(2)an estimated timetable for the execution of the project;
(3)a survey file on which the outline of the building is marked, together with a copy of the certification of a licensed surveyor regarding the marking of the outline of the building on the lot itself;
(4)(Repealed)
(5)(Repealed)
(6)attachments and other documents which, pursuant to the permit, are to be transmitted to the inspection institute before the commencement of execution of the works;
(7)a list of the laboratory tests carried out by the application author and the sub-authors, if appointed, in accordance with their respective professional areas of responsibility, and a copy of the engagement confirmation with an approved laboratory for the carrying out of the laboratory tests;
(8)an electronic file of architectural working plans coordinated with the plan files referred to in paragraphs (9) to (11), including marking of primary load-bearing elements, inter-storey passages, distribution boards, rainwater pipes, collectors, primary shafts, primary ducts for air conditioning and smoke evacuation, signed by the application author, and an accessibility authorised person's opinion if required under section 158f3 of the Law;
(9)an electronic file of a development working plan for execution coordinated with all the infrastructure on the lot;
(10)an electronic file of a structural working plan including, inter alia, a shoring plan, foundation plan, slab plans, columns, beams, and local cross-sections for the entire building including reinforcement and reinforcement details;
(11)an electronic file of a water and sewerage working plan including a complete water supply and fire-fighting schematic, wastewater and grey water schematics, details, the layout of water and sewerage lines, and sewerage cross-sections on a development background;
(12)(Repealed)
(13)the particulars of the person responsible for coordination with the inspection institute and the particulars of the person responsible for supervision of execution, including a copy of the notice of their appointment as referred to in regulation 71 of the Building Licensing Regulations;
(14)a declaration by the application author and the sub-authors, as the case may be, regarding the conformity of the documents detailed in paragraphs (3) to (11) with the permit and the design annexes, as the case may be;
(15)in an application for engagement with an inspection institute that includes the application of a new building method not detailed in the permit –
(a)an annex setting out the name of the method, its approval number, its period of validity, the date of its approval and the scope of its application as directed by the authorised body;
(b)a copy of the declaration of the person in charge of the new building method, stating that the proposed design conforms to the rules and conditions included in the temporary approval, or in the permanent approval;
(c)a copy of the confirmation by the holder of a new building method that the holder has reported to the authorised body of the intention to submit an application for commencement of works approval that includes a new building method;
(d)this sub-regulation shall apply to a person to whom the Licensing Regulations apply in respect of a new building method;
(16)a site visit schedule for all those required to carry out superior supervision, if the application author has prepared such a schedule.
(17)Notwithstanding the provisions of paragraphs (8) to (11), the person responsible for supervision of execution may, at the request of the permit holder, submit to the inspection institute the plan files detailed in those paragraphs at several dates in accordance with the following provisions:
(a)at the date of submission of the application for construction inspection, all of the following shall be submitted:
(1)the plan files required in respect of the part up to the defining entrance of the building as defined in the Permit Application Regulations; if the building includes two basement storeys or more, the plan files may be submitted up to the ceiling of the lowest basement storey, and at a later date the remaining plan files shall be submitted as referred to in this sub-paragraph;
(2)a list detailing the dates on which the remaining plan files will be submitted and the particulars of the plan files to be transferred at each date; such a list shall not include more than two submission dates;
(b)notwithstanding the provisions of sub-paragraph (a), in respect of a multi-storey building as defined in the Permit Application Regulations or in respect of a complex structure under the Fourth Schedule, the list shall not include more than three submission dates;
(c)the submission dates on the list shall be at least 30 days before the estimated date for the execution of the works to which the plan files relate;
(d)the inspection institute may at any time require a change to the submission dates on the list or to the content of the plan files.
Execution in Stages§
49.

Where the permit holder has requested to execute the works that are the subject of the permit in stages, or where it is stated in the permit that the work is to be executed in stages, the permit holder shall indicate this in the application for construction inspection and shall also detail the stages requested for execution.

Agreement for the Provision of Construction Inspection Services§
50.

Upon submission of an application for construction inspection to the inspection institute, the permit holder shall enter into an agreement with the inspection institute for the provision of construction inspection services, and shall pay the fee for construction inspection under Chapter VII and the Fifth Schedule.

Agreement for the Provision of Construction Inspection Services for Construction of Part of a Building, Additions or Alterations§
50a.
(a)For construction inspection in the construction of part of a building whose overall construction is subject to the obligation of inspection by an inspection institute, the fee shall be calculated according to the total construction area of the structure intended to be built.
(b)For construction inspection for the execution of additions or alterations under a building permit in respect of which inspection by an inspection institute applies but in respect of which a completion certificate has not yet been issued, provided that the building incorporating the additions or alterations is of a type in respect of which the obligation of inspection by an inspection institute applies, the fee for the construction addition shall be calculated according to the construction area added to the areas approved under the previous permit at the inspection institute.
(c)For construction inspection for alterations to the building under the previous permit, the fee shall be calculated in accordance with regulation 72.
Examination of an Application for Construction Inspection§
51.
(a)Where the permit holder has paid the payment for construction inspection, the inspection institute shall verify that all the documents required for construction inspection under regulations 48 and 49 have been submitted, within 15 days of the date of submission of the application, and the inspection institute shall be entitled to require explanations and additional documents as needed for its examination within the said period.
(b)In an application for construction inspection to which regulation 44(a)(1) applies, the examination period shall be 30 days.
Receipt of the Application§
52.
(a)Where an inspection institute finds, within the period referred to in regulation 51, deficiencies in the documents submitted, it shall notify the person responsible for supervision of execution, the application author and the permit holder thereof, shall detail what requires correction, and shall clarify that it is not possible to receive the application as submitted.
(b)Where all the documents referred to in regulations 48, 49 and 51 have been submitted and no deficiencies as referred to in sub-regulation (a) have been found, the application shall be received and notice thereof shall be given to the permit holder, the application author and the person responsible for supervision of execution.
(c)Where the inspection institute has not given notice of its decision within the period referred to in regulation 51, the permit holder shall be entitled to notify the inspection institute within 5 days of the date on which the said deadline has passed, of the termination of its engagement therewith, and to receive a refund of the fee paid as referred to in regulation 76(5).
Submission and Receipt of Working Plans in Stages in Construction Inspection§
52a.
(a)Where plan files have been submitted as referred to in regulation 48(17), the person responsible for supervision of execution shall submit to the inspection institute the remaining plan files in accordance with the submission dates set for that purpose on the list as referred to in that paragraph; within fifteen days of each submission date, the inspection institute shall verify that all the plan files required under the list as referred to in that paragraph have been submitted and examine their conformity, and shall notify the permit holder, the application author and the person responsible for execution of the results of its examination; where no deficiencies are found, it shall approve the plan files; where deficiencies are found, it shall detail what requires correction and shall clarify that it is not possible to commence execution of the work in accordance with the plan files until the deficiencies are corrected and approval is received from the inspection institute that the deficiencies have been corrected.
(b)Where work has been carried out without the inspection institute having approved the working plan files in respect thereof, the construction work carried out shall be deemed work not in accordance with the conditions of the permit, even if it does not deviate from those conditions, and it shall be treated as referred to in regulation 60.
Notice to the Licensing Authority§
53.

An inspection institute shall notify the licensing authority of the engagement and receipt of an application for construction inspection; the following documents shall be attached to its notice to the licensing authority:

(1)(Repealed)
(2)an estimated timetable for the execution of the project;
(3)the inspection institute's opinion on execution in stages if an application therefor was submitted or if it is stated in the permit that the work is to be executed in stages as referred to in regulation 49.
(4)a list of the submission dates for the working plan files as required in regulation 48(17), if the permit holder has chosen to submit the working plans at several dates.
Visit Schedule§
54.
(a)Where commencement of works approval has been granted under section 157b of the Law, the inspector responsible for construction inspection shall prepare the visit schedule within 5 days of the granting of such approval.
(b)The visit schedule shall contain, inter alia, milestones in execution and estimated target dates, including estimated visit dates according to stages of execution and areas of inspection, taking into account the following factors: the nature and complexity of the work, the detail of the design submitted, the rate of work and exceptional and hazardous characteristics.
(c)The visit schedule shall include each of the following stages, if they are included in the works that are the subject of the permit:
(1)before the commencement of execution of the works;
(2)during the execution of the foundation works;
(3)during waterproofing of the below-ground construction;
(4)during construction of the building's structural frame;
(5)completion of the structural frame;
(6)activation of systems and their combined operation, including finishing works in the structure.
(d)In addition to the provisions of sub-regulation (c), the person in charge shall publish on the website of the Planning Administration guidelines pursuant to the person in charge's authority under section 158ae1(d) of the Law regarding additional visits, taking into account, inter alia, the type of work, its scope and the intended use of the structure.
(e)Where an approving body has issued instructions for mandatory visits by an authorised inspector on its behalf, the visits shall be carried out, where possible, together with the visits referred to in sub-regulations (c) and (d).
(f)The visit schedule shall include all the visits detailed in sub-regulations (c) to (e).
Repeat Visits and Additional Visits§
55.

An inspection institute shall carry out repeat visits for the purpose of inspecting the correction of deficiencies and additional visits in the following cases:

(1)for the purpose of inspecting the correction of a deficiency found in a previous visit and the conformity of the work with the design requirements, where it is not possible to defer such inspection to the date of the next scheduled visit, given that the institute has found there is a real and immediate risk to the structure or its surroundings, or that deferring the visit may prejudice the ability to inspect the correction of the deficiency;
(2)upon the cessation of work due to an administrative order or a judicial order, or due to a decision by the permit holder to cease work at the site for a period exceeding 45 days, and shortly after the resumption of execution of the works in such cases;
(3)at the end of each stage and at the commencement of the next stage in cases where the permit holder has requested to execute the works that are the subject of the permit in stages, or where it is stated in the permit that the work is to be executed in stages;
(4)pursuant to a reasoned and detailed request by the committee engineer on the subject of building design as referred to in regulation 89.
Notice to the Inspection Institute§
56.

The person responsible for coordination with the inspection institute shall notify the inspection institute of all of the following:

(1)the state of progress of the works and their reaching the inspection stage planned in accordance with the visit schedule, at least five days before the works reach the next inspection stage in accordance with the visit schedule as referred to in regulation 54;
(2)the cessation of works and their resumption as referred to in regulation 55(2);
(3)the payment of the fee set at the time of the invitation to the inspection institute to carry out inspection at the structural frame completion stage as referred to in regulation 73(a)(3).
Work Required for Inspection§
57.

Any work that has been performed and is required for inspection by an inspection institute shall remain exposed until the end of the working day on which the inspection institute's visit is scheduled according to the inspection plan and according to the date notified by the person responsible for coordination with the inspection institute as referred to in regulation 56(1), or until the inspector's visit, whichever is earlier.

Tests during Execution§
58.

The construction inspection manager may require the performance of repeat or additional tests where he finds that the results of a test are not in order.

Inspection Log§
59.

A construction inspection log shall be maintained at the inspection institute, in a format directed by the person in charge, in which the information on construction inspection shall be consolidated, including:

(1)the inspection plan as referred to in regulation 54 and the notifications of the person responsible for coordination with the inspection institute as referred to in regulation 56(1);
(2)reports of visits that were carried out;
(3)test results and required approvals, as well as a list of the tests required by the inspection institute under regulation 60(a) and the reasons therefor;
(4)any change in execution, deviation, failure or defect discovered by any of the inspectors, as well as the reasons for the requirement for amended working plans, calculations, drawings or schematics as referred to in regulation 60(a), if required;
(5)repeat or additional visits required under regulation 55 and the reasons therefor;
(6)where work at the site was suspended as referred to in regulation 55(2), the inspection log shall include the inspector's report at the time of the closure of the site, including a description of the state of construction.
Non-Conformity with Design Instructions§
60.
(a)Where an inspector discovers a defect, error, lack of clarity or deviation from the design instructions in the execution of the works, or discovers the execution of works not approved by the inspection institute, he shall notify the person responsible for supervision of execution, the permit holder and the person carrying out overall supervision of the execution of the works under the permit, and he may summon to the site for clarification the principal application preparer or the relevant sub-preparer, and may direct the performance of the actions required for rectification and the timetables for performing the rectification, as well as direct the performance of laboratory tests to verify the conformity of the work, if required; at the request of an inspector, the person responsible for supervision of execution shall provide additional particulars regarding building components, building materials and installations in the building required for the risk assessment; where an inspector considers that the submission of amended working plans, calculations, drawings or schematics is required, he may so direct, provided that he gives written reasons for the need for such a requirement.
(b)The inspection institute shall carry out inspection of the execution of the rectification if required under sub-regulation (a), at the next scheduled visit according to the inspection plan, or at a repeat visit as referred to in regulation 55(1).
(c)Where the rectification has not been performed by the date directed by an inspector as referred to in sub-regulation (a), the construction inspection manager shall notify the committee engineer thereof and shall add his recommendation regarding the risks arising as a result.
Submission of Amended Working Plans§
61.
(a)The person responsible for supervision of execution may, at any time, submit to the inspection institute amended and updated working plans.
(b)The inspection institute shall notify the permit holder and the person responsible for supervision within five days of the date on which amended working plans were submitted to it as referred to in sub-regulation (a), of the inspection domains, from among the inspection domains detailed in regulation 88(a), that are affected by the amended plans, and whether the submission of calculations, drawings or schematics is required for the purpose of carrying out inspection of the amended plans.
Application for the Issuance of a Summarising Opinion for Construction Inspection§
62.

The permit holder shall submit to the inspection institute an application for the issuance of a summarising opinion for construction inspection required for the purpose of receiving an approval under section 157a(h4) of the Law, together with the test documents, documents and approvals required for the purpose of preparing a summarising opinion that have not yet been submitted to the inspection institute, and shall pay the balance of the fee prescribed in Chapter VII.

Summarising Opinion for Construction Inspection§
63.

Where an application as referred to in regulation 62 has been submitted and the documents and approvals required as referred to in regulation 62 have been attached thereto, and the balance of the payment under these Regulations has been paid, the construction inspection manager shall submit to the permit holder and to the licensing authority within 20 days a summarising opinion for construction inspection in which all of the following shall be detailed:

(1)details of the visits carried out by the inspection institute;
(2)the conclusions of the inspectors who carried out construction inspection, and whether the inspection was found to be in order; where the inspection was found not to be in order, the defects found shall be detailed;
(3)the conclusions of the authorised inspectors, if required, and whether the inspection was found to be in order; where the inspection was found not to be in order, the defects found shall be detailed;
(4)the results of the list of tests conducted by the application preparer as referred to in regulation 48(7), and additional tests if required under these Regulations; where not all test documents as referred to have been submitted to the inspection institute, or where it was found that the test results are not in order, the construction inspection manager shall detail the tests that have not yet been performed or that are not in order;
(5)details of design changes if made to the working plans under regulation 61 during the execution of the works;
(6)a recommendation to the licensing authority regarding the setting of conditions for the grant of a completion certificate, if required.