Natural Gas Sector Law, 5762-2002

חוק משק הגז הטבעי, תשס"ב-2002

Published: 2002-01-03Consolidated Hebrew text as of 2026-06-29 · Last amended 2026-03-31✓ Amendment status checked against the Knesset legislation record on 2026-11-10
Premium
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More

This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.

Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.

The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.

This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.

Section D: Revocation or Restriction of a Licence

Revocation or Restriction of a Licence§
19.
(a)The Director, after consultation with the Council and with the approval of the Minister, and after giving the licence holder an opportunity to state its arguments, may at any time revoke a licence if any of the following has occurred:
(1)the licence holder did not disclose to the tenders committee or to the Minister information that it was required to disclose in connection with participation in a tender or with the licence application, or provided incorrect information, all in respect of a material matter;
(2)a disqualifying circumstance for the receipt of the licence arose in the licence holder or a qualification condition required under this Law or under the licence conditions ceased to be fulfilled by it, and this was not rectified within a period determined by the Director in a notice sent to the licence holder;
(3)a winding-up order was made in respect of the licence holder or a receiver was appointed for it, and the order or appointment was not cancelled within a period determined by the Director in a notice sent to the licence holder;
(4)the licence holder did not comply with a direction to remedy defects or to carry out operations given to it under section 72, or committed a material breach of the licence and the breach cannot be remedied, and if the breach can be remedied, it was not remedied within the period determined by the Director or the Commissioner in a notice sent to the licence holder under section 72, and if the licence holder filed an objection under section 74 – within the period prescribed in the decision on the objection, and if the licence holder filed a petition under section 75 – it did not comply with the decision of the court;
(5)the licence holder committed a continuing breach of a provision under this Law or of the licence or of a condition of the licence, and the provisions of paragraph (4) shall apply;
(6)another ground prescribed in the licence as a ground for its revocation has arisen.
(b)The Director, after consultation with the Council and with the approval of the Minister, and after giving the licence holder an opportunity to state its arguments, may at any time restrict a licence in respect of its period of validity, the place or area in which the licence holder may operate, or any other restriction, if any of the conditions enumerated in subsection (a)(4) to (6) has been fulfilled.

Section E: Continuity of Activity and Transfer of Installations

Continuity of Activity and Appointment of a Supervisor§
20.
(a)Where the activity of a licence holder has ceased, or where the Minister finds that there is a real concern that its activity may cease, the Minister may give a direction for the purpose of maintaining continuity in the performance of the activity or resuming it, including directions that a licence holder is required to comply with even after the revocation or restriction of the licence.
(b)Where the activity of a licence holder has ceased, or where the Director finds that there is a real concern that a licence holder will be unable to continue carrying out its activity, the Director may, with the approval of the Minister, appoint a supervisor to carry out the activity until the cause giving rise to that concern has passed or until a licence is granted to another person who will continue the activity and to whom assets of the licence holder are transferred as set out in section 21, and prescribe the duties and powers of the supervisor (in this section – the supervisor).
(c)The appointment of the supervisor shall be made after the licence holder has been given an opportunity to state its arguments, unless the circumstances require, in the opinion of the Director, an urgent appointment.
(d)The supervisor shall be appointed for a period to be determined by the Director that shall not exceed one year; the Director, with the approval of the Minister, may extend the appointment for additional periods not exceeding six months at a time, and may also replace the supervisor at any time.
(e)The supervisor shall have all the powers necessary to ensure the performance of the activity, including the powers and duties of the general manager of the company holding the licence, of its board of directors and of the board of directors committees, and these shall not perform their duties or exercise their powers for as long as the appointment of the supervisor is in force, all subject to the directions given by the Director; the employees of the company shall comply with the directions of the supervisor; the licence holder shall pay the supervisor remuneration as directed by the Director.
(f)For as long as the appointment of the supervisor is in force, the company holding the licence, or a meeting of its shareholders or other rights holders, shall not adopt a resolution for its voluntary winding-up, except with the written consent of the supervisor.
Transfer of Assets§
21.
(a)In this section, "assets" means gas installations and other assets, whether tangible or intangible, as well as rights, required for the operation of gas installations.
(b)Subject to the provisions of subsections (c) and (d), if a licence has been revoked, or has expired and has not been renewed, or a liquidator or provisional liquidator has been appointed for the licence holder, or a receiver has been appointed for the licence holder or for its principal assets, assets that were used for its activity shall not be transferred to another, no right of use shall be vested therein, and no other person shall use them, except with the approval of the Director and on such conditions as the Director shall prescribe in order to ensure continuity of activity.
(c)If a licence has been revoked or has expired and has not been renewed, the assets shall, at that same date, pass into the ownership of the State, unless the Minister has directed the licence holder, with respect to the assets, in whole or in part, that they shall not be transferred as aforesaid; if the Minister has so directed, the Minister shall give directions to the licence holder with regard to the assets that have not been transferred to the State, including as to the manner in which the licence holder is to deal with the assets so that they do not constitute a risk or nuisance.
(d)If a licence has been granted in place of a licence that was revoked or that expired and was not renewed, the Minister may give directions to the previous licence holder with regard to the transfer of the assets, in whole or in part, to the new licence holder, and the Minister may also decide and give directions as to such transfer with regard to the assets whose ownership has passed to the State in accordance with the provisions of subsection (c).
(e)The transfer of assets as referred to in subsections (c) or (d) shall be without consideration unless otherwise specified in the licence; nothing in the provision of this subsection shall prevent the State from demanding payment from the new licence holder in respect of the transfer of the assets to it.
(f)In respect of assets for which it has been determined in advance in the conditions of the licence that they shall be transferred for consideration, the licence holder shall be entitled to payment therefor from the State or from the new licence holder, in accordance with the rules prescribed in the licence in that regard; the Director, in consultation with the Council, shall decide, in accordance with those rules, on the amount of the payment and the dates of its payment, after having given the previous licence holder an opportunity to be heard.
(g)(Repealed)
(h)The provisions of this section shall apply, with the necessary modifications, also to the restriction of a licence.

Section F: Transfer of a Licence and of Means of Control

Restrictions on Transfer of a Licence and Assets§
22.
(a)A licence, or any part thereof, is not transferable, chargeable as a security interest or attachable, in any manner whatsoever.
(b)Guarantees and undertakings furnished by a licence holder or a controlling shareholder therein pursuant to section 17(b)(2), and moneys received from their realisation, are not attachable or subject to a charge (security interest).
(c)Gas installations of the licence holder, as well as assets specified in the licence as required for the carrying out of the activity pursuant to the provisions of the licence, are not transferable, chargeable as a security interest or attachable, in any manner whatsoever, except with the prior written approval of the Director and on such conditions as the Director shall prescribe; the licence holder shall act to register in the registers and records maintained pursuant to any law the restrictions referred to in this subsection with regard to the assets to which they apply, and shall furnish to the Director confirmations of the registrations that have been effected.
(d)An act performed in contravention of the provisions of this section is void, and a court shall not order the conveyance of a right in a gas installation or in an asset as referred to in subsection (c) to another person, even if the licence holder did not act to register the restrictions as referred to in subsection (c); a person who has received into their possession a gas installation or asset as aforesaid is obliged to return it to the licence holder, and the licence holder shall return to that person what was received as consideration therefor or its value; if the Director has determined that the return of the gas installation or the asset is not possible in the circumstances of the matter, the person who received the gas installation or the asset shall return its value to the licence holder.
Transfer of Control and Means of Control§
23.
(a)A person shall not acquire or hold control or means of control in a licence holder in contravention of the provisions pursuant to section 8, or of provisions prescribed pursuant to subsection (b); a person holding control or means of control in a licence holder shall not transfer them to another in contravention of the provisions pursuant to section 8, or in contravention of provisions prescribed pursuant to subsection (b).
(b)The Minister may prescribe in Regulations or in a licence conditions and restrictions (in this section – provisions) for the transfer or acquisition of control and of means of control in a licence holder, and for the creation of a charge (security interest) over such means of control, to the extent the Minister considers necessary to ensure the interests of consumers and to maintain the provisions pursuant to section 8; if it has been prescribed as aforesaid that a transfer, acquisition or charge (security interest) requires approval, the approval shall be granted by the Minister with the consent of the Council.
(c)A person holding means of control in contravention of the provisions pursuant to section 8 or of provisions prescribed pursuant to subsection (b) is not entitled to exercise the rights by virtue thereof.
(d)The Minister may prescribe in Regulations or in a licence that a structural change or reorganisation of the licence holder, including a merger, split, compromise, arrangement or voluntary winding-up, requires the approval of the Minister with the consent of the Council.
(e)
(1)An interested party in a licence holder shall report to the licence holder on the conveyance of a right to another in the means of control held by such party, in whole or in part; for this purpose, "interested party" has the meaning given to it in the Securities Law, 5728-1968;
(2)a licence holder shall report to the Director, to the best of its knowledge, on every change in the particulars required to be registered in its shareholders register, as well as on any other information received pursuant to paragraph (1);
(3)a report as referred to in this subsection shall be made within 3 business days after the date of the conveyance of the right as referred to in paragraph (1) or after the licence holder became aware of the change as referred to in paragraphs (1) and (2), as the case may be.
(f)Determinations of the Minister pursuant to this section that were not prescribed in advance in the conditions of the licence shall be made after the licence holders concerned have been given an opportunity to be heard.

Chapter III: Construction of Gas Installations and Alterations thereto, and Compensation

Obligation to Submit a Specification and Its Approval by the Authority§

24.
(a)A licence holder shall not construct a gas installation or make an alteration therein except in accordance with a specification as referred to in subsection (b) (in this Chapter – specification) that has been approved by the Director and the Superintendent.
(b)A licence holder wishing to construct a gas installation or to make an alteration therein shall prepare and submit to the Authority a specification, which shall include the engineering plans and description of the works for the construction of the installation, and the description of the real property required for it and the particulars of ownership thereof, all as prescribed by the Minister in Regulations or in the licence; the Minister may prescribe in Regulations or in the licence additional particulars and documents to be included in the specification.
(b1)The Minister, with the consent of the Minister of Finance and with the approval of the Economics Committee of the Knesset, shall prescribe provisions regarding –
(1)a fee for the submission of a specification or amendments to a specification;
(2)modes and dates of payment of the fee, including its linkage to the Consumer Price Index published by the Central Bureau of Statistics and the setting of default interest.
(c)If the Director and the Superintendent have found that the specification meets the conditions prescribed in safety Orders, in Regulations made pursuant to this Law and in the conditions of the licence, they shall approve the specification; if the Director or the Superintendent has found that the specification does not meet the conditions as aforesaid, the Director or the Superintendent may require the licence holder, after having given the licence holder an opportunity to be heard, to amend the specification or to comply with directions to be issued so as to ensure that the specification meets those conditions.
(c1)With regard to a specification submitted in connection with the construction or alteration of a distribution network, the Director and the Superintendent shall notify their decision pursuant to subsection (c) within 30 working days from the date of submission of the specification, provided that the specification has met the requirements pursuant to subsection (b); if a specification meeting the requirements as aforesaid has been submitted and the submitter has been required to make additions to the specification, the Director and the Superintendent shall notify their decision as aforesaid within 7 working days from the re-submission of the specification.
(d)The Director may prescribe in rules categories of alterations to a gas installation that do not require the submission of a specification and approval pursuant to this section; the rules pursuant to this subsection shall be published in Reshumot (Official Gazette).
(e)Approval pursuant to this section is in addition to any approval or permit required pursuant to any law, including pursuant to the Planning and Building Law, and it does not vest rights in real property or the right to demand the acquisition of rights in real property.

Work Plan for a Distribution Network§

25.
(a)In this Law –

"Licensing Authority" means the Licensing Authority for Natural Gas Installations as referred to in section 119f of the Planning and Building Law;

"work plan" means a map including the marking of the location of a gas installation that is part of a distribution network, as well as written provisions.

(b)A work plan shall be approved by the Licensing Authority; the Licensing Authority shall not make the submission of a work plan conditional on the approval of a specification pursuant to section 24, provided that a work plan shall not be approved except after the approval of the specification.
(c)If a work plan has been submitted for the approval of the Licensing Authority in accordance with the Regulations pursuant to subsection (o), the Licensing Authority shall decide within 30 days from the date of its submission whether to publish it for public objections, to make the publication thereof as aforesaid conditional on conditions, or to reject it.
(d)The Licensing Authority shall not make the publication of a work plan for objections conditional on conditions, unless it has considered that the conditions can be met or are expected to be met within 30 days from the date of delivery of the notice of its decision to the submitter of the work plan.
(e)The Licensing Authority shall notify the submitter of the work plan of its decision pursuant to subsection (c), within three days from the date of the decision.
(f)If the Licensing Authority has decided to publish the work plan subject to conditions, the submitter of the plan may submit to it, within ten days from the date of receipt of the decision, a request to amend or cancel conditions that it reasonably considers cannot be met within 30 days as referred to in subsection (d); if such a request has been submitted, the Licensing Authority may, within seven days from the date of submission of the request and after having considered the request, leave its decision as it is, amend the conditions for publication, or reject the work plan.
(g)The Licensing Authority shall notify the submitter of the work plan of its decision pursuant to subsection (f), within three days from the date of the decision.
(h)If the Licensing Authority has decided to publish a work plan for public objections as referred to in subsection (c), it shall publish, within seven days from the date of the decision or from the date on which the conditions for publication were met, if any were prescribed, whichever is later –
(1)the work plan on the website of the Planning Administration and shall make it available for public inspection at the offices of the District Committee, and shall also transmit the plan to the relevant Local Committees for the purpose of making it available for public inspection at their offices;
(2)a notice of the publication of the work plan for objections –
(a)in a newspaper pursuant to the provisions of section 1a of the Planning and Building Law;
(b)at the offices of the local authorities whose jurisdiction, or part thereof, is included within the area of the work plan;
(c)at the offices of the District Committee whose planning area, or part thereof, is included within the area of the work plan.
(i)A person who considers themselves aggrieved by a work plan may submit an objection thereto within 30 days from the day on which the plan was published pursuant to subsection (h)(2)(a); the objection shall be submitted to the Licensing Authority and a copy thereof shall be sent to the Local Committee whose planning area, or part thereof, is included within the area of the work plan.
(j)If public objections have been submitted as referred to in subsection (i), the Licensing Authority shall consider them within 30 days from the end of the period for their transmission as referred to in that subsection, and shall decide whether to approve or reject the work plan; such approval may be conditional on the amendment of the plan or on such conditions as the Licensing Authority shall prescribe.
(k)The Licensing Authority shall not make its approval of a work plan conditional on conditions, unless it has considered that the conditions can be met or are expected to be met within 30 days from the date of delivery of the notice of its decision to the submitter of the work plan.
(l)If a work plan has been published for public objections as referred to in subsection (h), and no objections thereto have been submitted within the period prescribed therefor, the plan shall be deemed approved.
(m)The provisions of sections 103a, 104, 106(b) to (d), 107 and 108(b) of the Planning and Building Law shall apply for the purposes of this section, with the necessary modifications.
(n)Notwithstanding the provisions of section 24(e), a work plan approved pursuant to this section shall replace the approval of a plan pursuant to the Planning and Building Law.
(o)The Minister of Finance, with the approval of the Economics Committee of the Knesset, shall prescribe provisions regarding the manner of submission of a work plan and regarding the particulars to be included therein.

Deliberation on a Work Plan in the Sub-Committee for Work Plans§

25a.
(a)If the Licensing Authority has not made a decision pursuant to section 25(c), (f) or (j) within the periods prescribed in that section, or has decided to reject the work plan pursuant to the provisions of section 25(c) or (f), the submitter of the work plan may transfer the work plan for approval by the Sub-Committee for Work Plans as referred to in section 119g of the Planning and Building Law (in this section – the Committee), within 30 days from the end of the period for making the said decisions or from the date of the decision to reject the plan as aforesaid, as the case may be.
(b)If a work plan has been transferred to the Committee as referred to in subsection (a) –
(1)the powers of the Licensing Authority with regard to that plan shall be vested in the Committee;
(2)the provisions applicable to the proceedings before the Licensing Authority pursuant to section 25 shall apply to the proceedings before the Committee, with the necessary modifications and with the following modification: in section 25(o), instead of "submission of a work plan" read "transfer of a work plan for deliberation by the Sub-Committee for Work Plans as referred to in section 25a";
(3)by reason of the failure of the Licensing Authority to make a decision within the period prescribed in section 25(c) or (f), or the rejection of the plan as referred to in those sections – the date of transfer of the work plan to the Committee shall be deemed to be the date of submission of the work plan;
(4)by reason of the failure of the Licensing Authority to make a decision within the period prescribed in section 25(j) – the date of transfer of the work plan to the Committee shall be deemed to be the date on which the period for the transmission of public objections to the work plan as referred to in section 25(i) has expired.

Construction of a Gas Installation at Very Low Pressure§

26.
(a)The location of a gas installation that is part of a distribution network at very low pressure, to the extent not determined in a work plan, shall be determined in a specification approved as referred to in section 24, and shall require the approval of the Local Licensing Authority, as referred to in the Planning and Building Law, in the local planning area in which the gas installation is to be constructed; in this subsection, "very low pressure" means pressure of 4 bar or less.
(b)The Minister of the Interior, with the approval of the Economics Committee of the Knesset, shall make Regulations regarding the procedures for the submission of a specification and the procedures for its approval as referred to in subsection (a), and may also prescribe provisions regarding additional particulars or documents to be attached to the specification submitted for the approval of the Local Licensing Authority, provided that if the Local Licensing Authority has not given its decision within 60 days from the day on which the specification was submitted to it, the specification shall be deemed to have been approved by it.
(c)If the Local Licensing Authority has refused to approve the specification, the applicant may appeal to the Appeals Committee as referred to in section 12a of the Planning and Building Law within 15 days from the day on which the refusal was notified to the applicant.

Definitions for sections 26b to 26k – Fast-Track Procedure§

26a.

In this section and in sections 26b to 26k –

"application" – an application for approval under the fast-track procedure submitted pursuant to the provisions of section 26c;

"the approving authority" – the committee engineer, however –

(1)in respect of a gas installation that is not within a local planning area – the district planner;
(2)if comments of a landowner were received pursuant to the provisions of section 26d – the local licensing authority;

"fast-track procedure" – a procedure for the approval of the construction of a gas installation that forms part of a distribution network pursuant to the provisions of sections 26b to 26k;

"restrictions" – building, development and use restrictions applying to the real property by reason of the construction of a gas installation pursuant to a safety order in respect of a distribution network;

"committee engineer" – the engineer of the local planning and building committee, as defined in section 20 of the Planning and Building Law, of the local committee within whose planning area the area of the application is located;

"transition point installation" – a meter and pressure-reduction installation as defined in section 37(b);

"infrastructure installation" – each of the following, including installations serving them:

(1)roads and railways of all types;
(2)infrastructure lines, including electricity lines, liquefied petroleum gas lines or lines carrying chemicals and fuel of all types or hazardous materials;
(3)communication lines;
(4)water lines, sewage lines and drainage lines;

"local planning area" – as defined in section 13 of the Planning and Building Law;

"district planner" – as defined in section 8(a) of the Planning and Building Law, of the district within whose boundaries it is proposed to construct the gas installation;

"local licensing authority" – as defined in section 30 of the Planning and Building Law, in the local planning area in which it is proposed to construct the gas installation;

"area of the application" – the area required for the construction of the gas installation and the area to which the restrictions will apply, all as set out in the application.

Expedited Procedure for the Construction of a Gas Installation in a Distribution Network§

26b.

Notwithstanding the provisions of sections 25 and 26, the approving authority is competent to approve the construction of a gas installation that is part of a distribution network under the expedited procedure, if all of the following conditions are met with regard to the gas installation:

(1)the gas installation is intended to connect between a distribution network for which the required approvals pursuant to this Chapter have been granted or which was constructed pursuant to a plan under the Planning and Building Law, and a consumer; for this purpose, a gas installation shall be regarded as an installation intended to connect between a distribution network and a consumer, even if the location of the connection to the distribution network and the location of the connection to the consumer are not in the same local planning area;
(2)the installation is planned for the flow of gas at a pressure not exceeding 7 bar;
(3)the gas installation is to be constructed on the consumer's premises or on land whose designation is one or more of the following:
(a)land designated as a road;
(b)land designated as an open public area;
(c)land designated as engineering installations;
(d)land designated as agricultural;
(4)restrictions not on the consumer's premises shall apply only on land or in an area as referred to in paragraph (3);
(5)the gas installation to be constructed other than on the consumer's premises shall be underground only, except for the above-ground part of a manhole for a shut-off valve;
(6)the length of the gas installation to be approved shall not exceed 10,000 metres; for the purposes of this paragraph, "the length of the gas installation" means the length of the infrastructure of the largest gas installation, measured from the point of connection to the distribution network whose approval was granted other than under the expedited procedure, to the transition point installation that is part of the gas installation for which approval under the expedited procedure is sought, plus the restriction distances applying by reason of those installations as aforesaid.

Submission of an Application under the Expedited Procedure§

26c.
(a)An application shall be submitted by a distribution licence holder (in sections 26c to 26k – the applicant) to the Committee Engineer, and with regard to a gas installation in a district planning area, as referred to in section 12 of the Planning and Building Law – to the District Planner.
(b)
(1)The submission of an application is conditional on the applicant approaching all holders of infrastructure installations in the area of the application, at least 15 days before the submission of the application, for the purpose of obtaining information regarding the infrastructure installations in the area of the application and their response thereto; the approach shall be sent digitally, and in accordance with the provisions of item 1 of the Second Schedule;
(2)if the applicant has not received information on the infrastructure installations and a response to the application within the period referred to in paragraph (1), the applicant may submit the application.
(c)An application shall include the information and documents listed in the First Schedule; the approving authority is not entitled to require the applicant to provide additional documents, particulars or attachments beyond those referred to in this section and in section 26d.
(d)The application shall be signed by the applicant; without derogating from the foregoing, every document among the documents of the application or its annexes shall be signed by the person who prepared it.

Submission of Comments on an Application in an Expedited Procedure§

26d.
(a)The owner of an infrastructure installation and the owner of real property within the area of the application may submit their comments on the application to the committee engineer or to the district planner to whom the application was submitted, as the case may be; comments on an application under this section shall be submitted within 15 days of the date of delivery of the notice in accordance with the provisions of subsection (b); if the committee engineer or the district planner, as the case may be, receives comments on the application, he shall send a copy thereof to the applicant.
(b)Promptly after the submission of the application, the applicant shall notify all owners of infrastructure installations and owners of real property within the area of the application of its submission; such notice to an owner of an infrastructure installation shall be sent digitally; such notice to an owner of an infrastructure installation or to an owner of real property shall be delivered or sent in accordance with the provisions of section 2 of the Second Schedule.
(c)If the committee engineer or the district planner to whom the application was submitted has not received the comments of an owner of an infrastructure installation or an owner of real property on the application within the period prescribed therefor, the owner of the infrastructure installation or the owner of the real property shall be deemed to have no comments on the application, and the engineer or planner referred to shall decide on the application in accordance with the provisions of section 26e; if the comments of an owner of an infrastructure installation have been submitted to the engineer or planner referred to, he shall decide on the application in accordance with the provisions of section 26e; if the comments of an owner of real property have been submitted to the engineer or planner referred to within the period prescribed therefor, he shall transfer the comments received to the local licensing authority for the purpose of its decision on the application, in accordance with the provisions of section 26e.

Decision on an Application in an Expedited Procedure§

26e.
(a)The approving authority shall decide whether to approve an application, to approve it subject to conditions in accordance with the provisions of subsection (b), or to reject it, within 30 days of the end of the period for the transfer of comments in accordance with the provisions of section 26d.
(b)
(1)If the approving authority approved the application subject to conditions, it shall not impose conditions save in matters relating to the manner of carrying out the requested work or to the matter of restoring the area within which the work is carried out to its former state after completion of the work; such conditions shall be imposed in respect of one or more of the following subjects only:
(a)fillings and excavations;
(b)fencing for safety purposes during the carrying out of the works;
(c)preservation of trees, plants and wildlife within the area of the application;
(d)in an application whose area includes land designated as an open public space — prevention of significant harm to the environment;
(e)adoption of safety measures for the protection of the public;
(f)prevention of disruption to the public during the work, including disruption to vehicular and pedestrian traffic on a public road;
(g)conditions for the removal of construction waste during and upon completion of the work;
(h)prevention of harm to an infrastructure installation or to an installation of the local authority;
(i)restoration of the area within which the work is carried out to its former state after completion of the work, including the setting of a reasonable guarantee in the circumstances of the matter for that purpose;
(j)a requirement for the presence of a representative of the local authority or a person on its behalf during the carrying out of the works, for the purpose of supervising compliance with the conditions referred to in this subsection;
(2)If the approving authority has imposed conditions in accordance with the provisions of paragraph (1), it shall not include in those conditions a requirement for coordination with or consultation with an owner of an infrastructure installation that is not a local authority or a municipal corporation, as defined in section 249a of the Municipalities Ordinance, or a condition requiring the approval of such an infrastructure owner.
(c)The decision of the approving authority on the application shall be guided by planning considerations and by the plans applicable under the Planning and Building Law, having regard to the comments of the owner of real property, to the possibility of harm to land designated as an open public space included within the area of the application, or to the possibility of harm to another infrastructure that may cause serious environmental harm, and in accordance with these alone.
(d)If the decision of the approving authority has not been received within five days of the end of the period prescribed in subsection (a) for the making of a decision by the approving authority, the application shall be deemed to have received approval in an expedited procedure, and the applicant shall send notice thereof to the parties listed in subsection (e)(2) and (3).
(e)An approving authority shall deliver a copy of its decision under this section within five days of the date of its making, to each of the following:
(1)the applicant;
(2)the Natural Gas Authority;
(3)an owner of an infrastructure installation who provided information or a response in accordance with the provisions of section 26c(b), and an owner of an infrastructure installation or an owner of real property who submitted comments on the application in accordance with the provisions of section 26d.

Deliberation on an Application in an Expedited Procedure before the Licensing Authority or the Subcommittee for Work Plans§

26f.
(a)If the approving authority decided to reject the application or to approve the application subject to conditions, the applicant may transfer the application for approval by the licensing authority, whose composition for this purpose shall not include the committee engineer, and if the approving authority is the district planner — to the committee as defined in section 25a(a) (in this section — the committee).
(b)The applicant shall transfer the application as referred to in subsection (a) within 15 days of the date on which the decision of the approving authority was delivered to him, shall set out the reasons for the transfer, and shall attach thereto all the documents that were submitted in the matter to the approving authority, including the documents referred to in sections 26c and 26d, and the decision of the approving authority.
(c)If the applicant transferred the application as referred to in subsection (a), he shall deliver notice thereof to the approving authority digitally, together with the reasons for the transfer; the approving authority may transmit its position on the application that was transferred as aforesaid, digitally, within seven days of the date on which the notice was delivered to it.
(d)The licensing authority or the committee, as the case may be, shall decide whether to approve the application, to approve it subject to conditions as referred to in section 26e(b), or to reject it within 30 days of the date on which the position of the approving authority was transmitted as referred to in subsection (c), or within 30 days of the date on which the time for transmitting its position as aforesaid has elapsed, whichever is earlier; the licensing authority or the committee, as the case may be, shall send the decision to the applicant, the approving authority, the Natural Gas Authority and the local committee whose planning area includes the area of the application.
(e)For the purpose of a decision on an application under this section, the powers of the approving authority shall be vested in the licensing authority or the committee, as the case may be, and the provisions of section 26e(b) and (c) shall apply to the decision.
(f)The Director of the Authority, or an employee of the Authority whom he has authorised for this purpose, shall be invited to the deliberation on the application under this section, and shall be entitled to express the position of the Authority in relation to the application.

Validity of Approval in an Expedited Procedure§

26g.
(a)The validity of an approval in an expedited procedure is three years from the date on which it was granted.
(b)If work has not been commenced within one year of the date of the grant of an approval in an expedited procedure — the approval is void; however, the approving authority may renew it, at its discretion and upon the request of the applicant.

Coordination with the Local Authority for the Purpose of Fulfilling a Condition in an Approval in an Expedited Procedure or Obtaining Its Approval§

26h.

If the approving authority has prescribed in its decision a condition pursuant to which coordination with the local authority or a person on its behalf, or with a municipal corporation as defined in section 249a of the Municipalities Ordinance (in this section — the local authority), or the obtaining of the approval of the local authority, is required, the following provisions shall apply:

(1)If the applicant approached the local authority, the local authority shall respond to the applicant's approach, on its merits, within 30 days of the date on which the approach was received;
(2)If the local authority responded to the applicant that he must submit supplementary materials for the purpose of fulfilling the said condition, and the applicant transferred such supplementary materials to it, it shall respond to him, on the merits of the matter, within 15 days of the date on which he submitted the required supplementary materials to it;
(3)If the local authority did not respond to the applicant as referred to in the provisions of paragraph (1) or (2) and within the periods prescribed therein, the condition prescribed in the decision of the approving authority shall be deemed to have been fulfilled.

As-Built Survey Map Following the Carrying Out of Works in an Expedited Procedure§

26i.
(a)Upon completion of the carrying out of the works for the construction of a natural gas installation pursuant to an approval in an expedited procedure, the applicant shall submit an as-built survey map, in accordance with the provisions of section 261(d)(4) of the Planning and Building Law, to each of the following:
(1)the committee engineer, and if the committee within whose area the gas installation was constructed is a local committee pursuant to section 19 of the Planning and Building Law — also the engineer of the local authority within whose area the gas installation was constructed;
(2)the National Fire and Rescue Authority, as defined in the National Fire and Rescue Authority Law, 5772-2012;
(3)the Natural Gas Authority.
(b)The as-built survey map shall indicate the restrictions that shall apply by reason of the location of the gas installation as constructed.

Manner of Submission and Transfer of an Application and Manner of Delivery of a Notice or Decision in an Expedited Procedure§

26j.
(a)The submission of an application and the transfer of an application in accordance with the provisions of section 26f shall be carried out digitally; a notice or decision of an approving authority or of a body that decided on an application in accordance with the provisions of section 26f shall be delivered digitally.
(b)The Director of the Planning Administration as defined in the Planning and Building Law (hereinafter — the Planning Administration), with the consent of the Director of the Natural Gas Authority, may, if he considers it necessary, publish on the website of the Planning Administration a notice regarding the digital manner of submission, transfer or delivery as referred to in subsection (a); if guidelines have been published in accordance with the provisions of this subsection, the documents referred to shall be submitted, transferred or delivered in accordance with the published guidelines.

Forms in an Expedited Procedure§

26k.

The Director of the Planning Administration, with the consent of the Director of the Natural Gas Authority, may, if he considers it necessary, publish on the website of the Planning Administration forms for the purpose of implementing the provisions of sections 26b to 26j, which shall include the details of information required under those sections, and those details alone; if forms have been published in accordance with the provisions of this section, the documents referred to shall be submitted in accordance with the forms as published.

Installation Constructed without Approval§

27.
(a)If a gas installation was constructed or altered without an approval or permit as required under this Law or the Planning and Building Law, the Commissioner may, by Order, prohibit or restrict the use of the installation, and also direct that the installation be emptied of gas; nothing in the foregoing shall derogate from any power under any law.
(b)An Order under this section shall be made after the owner of the installation has been given an opportunity to state his arguments, unless the circumstances require, in the opinion of the Commissioner, urgent action.

Compensation in respect of a Plan§

28.
(a)In this section —

"owner of real property" — includes the holder of a right in real property;

"plan for a gas installation" — a plan under the Planning and Building Law, which is not one of the plans for the transmission system, whose main purpose is the designation of real property for a gas installation, as well as a work plan;

"another plan" — a plan under the Planning and Building Law which is not a plan for a gas installation and is also not one of the plans for the transmission system, but which also includes the designation of real property for a gas installation.

(b)If real property situated within the area of a plan for a gas installation, or real property adjoining it, has been injuriously affected by such a plan, otherwise than by way of expropriation, the following provisions shall apply, notwithstanding the provisions of Chapter IX of the Planning and Building Law:
(1)the person who was the owner of the real property on the day of the coming into force of the plan shall be entitled to compensation from the licence holder for whose installations the plan was intended (in this section — the licence holder), provided that a claim for compensation was submitted to the licence holder within five years of the day of the coming into force of the plan or within one year of the date of delivery of a notice of intention to enter the real property under section 50 or of the date of publication of a notice under section 5 of the Land Requisition Ordinance, whichever is later;
(2)upon the demand of the owner of real property, the licence holder shall notify him, within sixty days of the date of the demand, of the amount of compensation that he proposes to pay and of the reasons for the amount proposed;
(3)if the owner of real property and the licence holder have agreed on the amount of compensation to be paid under this section, the licence holder shall pay him the agreed compensation within thirty days of the date of the agreement or at another time agreed upon by them;
(4)if the owner of real property and the licence holder have not agreed on the amount of compensation to be paid under this section, either of them may refer the matter for determination by the appeals committee (in this section — the claim); however, within thirty days of the date of submission of the claim as aforesaid, the licence holder shall pay the owner of real property the amount of compensation that is not in dispute; a person submitting a claim under this paragraph shall deliver a copy thereof to the other party;
(5)the provisions of sections 200 to 202 of the Planning and Building Law shall apply to the claim and to the compensation under this section;
(6)the appeals committee shall deliberate on the claim and decide, within 90 days of the date of submission of the claim, whether to accept or reject it, and if it decided to accept it — shall determine the amount of compensation; the appeals committee may, before making a decision as aforesaid, obtain the opinion of a valuer after the parties have been given an opportunity to argue their arguments in respect of the valuer's opinion; the appeals committee shall notify the parties of its decision and of its reasons;
(7)the decision of the appeals committee may be appealed to the Administrative Affairs Court.
(c)If real property situated within the area of one of the plans for the transmission system, or real property adjoining it, has been injuriously affected by such a plan, otherwise than by way of expropriation, the provisions of subsection (b) shall apply; however, if the licence holder for whose installations the plan was intended is the first transmission licence holder, selected as referred to in section 104 —
(1)the claim referred to in subsection (b)(1) shall be submitted to the Director, and for this purpose subsection (b)(2), (3), (4) and (6) shall be read as if "the State" were substituted for "the licence holder";
(2)the compensation to the owner of real property shall be paid from the State Treasury.
(d)If real property in which the gas installation is situated, or real property adjoining it, has been injuriously affected by the approval of a specification under section 26, the provisions of subsection (b) shall apply, with the following modification: instead of "the day of the coming into force of the plan" there shall come "the day of the approval of the specification by the local licensing authority".
(d1)If real property in which the gas installation is situated, or real property adjoining it, has been injuriously affected by an approval in an expedited procedure, the provisions of subsection (b) shall apply, with the following modification: instead of "the day of the coming into force of the plan" there shall come "the day of the receipt of an approval in an expedited procedure".
(e)If real property situated within the area of another plan, or real property adjoining it, has been injuriously affected by such a plan, otherwise than by way of expropriation, the provisions of Chapter IX of the Planning and Building Law shall apply, subject to the following provisions:
(1)if the local committee decided to accept the claim, it shall determine what part of the amount proposed for compensation is attributable to the designation of the real property for a gas installation; the committee may determine that there is no such part;
(2)the licence holder in whose hands the gas installation in the plan is intended to be operated shall indemnify the local committee in respect of the compensation it paid as a result of the designation of the real property for a gas installation, in the part of the amount determined under paragraph (1), if determined;
(3)if the licence holder disputed the determination of the local committee under paragraph (1), he may appeal to the appeals committee within 30 days of the date of delivery of the determination;
(4)if an appeal was submitted under section 198(d) of the Planning and Building Law, and the appeals committee accepted the appeal, it shall also determine what part of the amount of compensation is attributable to the designation of the real property for a gas installation; if a binding valuer was appointed under section 198(e) or (f) of the Planning and Building Law, the binding valuer may also decide what part of the amount of compensation is attributable to the designation of the real property for a gas installation; for the purpose of an appeal against a decision of a binding valuer under this paragraph and for the purpose of an appeal against a decision of an appeals committee under this paragraph, they shall be deemed to be decisions under section 198 of the Planning and Building Law and the provisions of subsections (e)(4) or (h) of that section shall apply, as the case may be.
(f)If an owner of real property is entitled to submit a claim in respect of the same injurious affection under more than one of subsections (b) to (e) of this section, he may submit a claim under only one of them, at his choice.

Compensation in respect of a National Outline Plan for the Receipt and Treatment of Natural Gas in the Absence of a Licence Holder for whose Installations the Plan is Intended§

28a.
(a)In this section –

"owner of real property" – as defined in section 28(a);

"holder of the national transmission licence" – the holder of a transmission licence granted pursuant to the provisions of section 11a;

"linkage differentials", except for the purposes of subsection (f)(3)(e) – an addition to the amount of compensation at the rate of increase of the Consumer Price Index published by the Central Bureau of Statistics shortly before the date of payment of the compensation or receipt of the indemnification funds and up to the index published shortly before the payment of the indemnification, the deposit of the indemnification funds or the payment of the amount equal to the compensation, as the case may be;

"day of commencement of construction" – the day on which the installer of the installation or a person on its behalf first entered the relevant real property for the purpose of performing one of the actions listed in paragraphs (2) to (4), (6) and (7) of section 49 in respect of the installation it is constructing;

"installation" – an installation serving for the receipt, transmission, distribution, supply, storage, measurement or pressure modification of petroleum as defined in the Petroleum Law, including a pipeline, structure, machine, instrument, accessory and fixed or movable equipment serving the installation;

"plan for the receipt and treatment of natural gas", "the plan" – a detailed-level national outline plan for the receipt and treatment of natural gas – from offshore discoveries to the national transmission system.

(b)Where the plan for a gas installation from which the real property was harmed, other than by way of expropriation as referred to in section 28, is a plan for the receipt and treatment of natural gas, and there is no licence holder for whose installations the plan is intended as referred to in subsection (b)(1) of that section, the provisions of subsection 28(b) shall apply with the modifications set out in subsections (c) to (i).
(c)An owner of real property that has been harmed shall be entitled to compensation pursuant to section 28(b)(1) from the person who constructed an installation by virtue of the plan (in this section – the installer of the installation), in respect of the harm from the part of the plan intended for the installation; in respect of the part of the plan not intended for an installation that has been constructed, or if no such installation has been constructed – the owner of the real property shall be entitled to compensation as aforesaid from the holder of the national transmission licence.
(d)The provisions of section 28(b) and section 29 that apply in respect of a licence holder shall apply to the installer of the installation or to the holder of the national transmission licence, as the case may be.
(e)The holder of the national transmission licence shall pay the compensation to the owner of real property pursuant to subsection (c) from an account with a banking corporation in which an amount collected in accordance with a tariff set by the Council pursuant to section 36(b2) is deposited, and subject to the conditions and provisions pursuant to that section; in this subsection, "banking corporation" – as defined in the Banking (Licensing) Law, 5741-1981.
(f)
(1)Where the holder of the national transmission licence has paid compensation to an owner of real property pursuant to this section and after the payment the construction of an installation by virtue of the plan in respect of which the real property was harmed has commenced, the installer of the installation shall indemnify the holder of the national transmission licence, within one month from the day of commencement of construction of the installation, in respect of the compensation paid on account of the harm from the part of the plan intended for the installation, in accordance with the amount of compensation paid by the holder of the national transmission licence as aforesaid, plus linkage differentials from the day of payment of the compensation to the date of payment of the indemnification;
(2)the holder of the national transmission licence shall deposit the indemnification funds in the account referred to in subsection (e) no later than one week from the day it received those funds, plus linkage differentials from the day of receipt of the indemnification funds to the date of their deposit;
(3)where there is no agreement on the amount of the indemnification or the amount of the indemnification has not been paid in full by the date referred to in paragraph (1), the following provisions shall apply:
(a)the installer of the installation or the holder of the national transmission licence shall bring the matter before the Director of the Authority within one month from the day on which the installer of the installation was required to indemnify the holder of the national transmission licence;
(b)no claim relating to the tariff set by the Council as referred to in subsection (e) shall be heard;
(c)the Director of the Authority shall decide the dispute after consulting with the Council, and notwithstanding the provisions of sub-paragraph (a), the Director may decide the dispute even if the matter was not brought before the Director in accordance with that sub-paragraph; the Director's decision together with its reasons shall be delivered to the installer of the installation and to the holder of the national transmission licence;
(d)where the Director has decided that the installer of the installation is required to pay any indemnification amount to the holder of the national transmission licence, the Director shall include in that amount the linkage differentials from the day of payment of the compensation to the day of the Director's decision; where the Director has permitted the amount to be paid by a date later than the day of the Director's decision, the amount shall bear linkage differentials from the day of the decision to the date on which the amount was paid or to the last date by which the Director permitted payment of the amount, whichever is earlier;
(e)to an amount as referred to in sub-paragraph (d) there shall be added shekel interest and arrears charges, from the day of the Director's decision and, if the Director permitted the amount to be paid at a date later than the day of the Director's decision – from that date until the day of payment, and the provisions of the Interest and Linkage Decision Law shall apply, with the necessary modifications;
(f)the holder of the national transmission licence shall deposit funds received pursuant to sub-paragraphs (d) and (e) in the account referred to in subsection (e) no later than one week from the day it received those funds, plus linkage differentials from the day of their receipt to the date of their deposit;
(g)where the amount has not been paid in accordance with sub-paragraphs (d) and (e), the holder of the national transmission licence shall take the steps required to collect it, and shall deposit the amount collected in the account from which the compensation was paid in accordance with subsection (e); without derogating from the collection obligation imposed on the holder of the national transmission licence, where the Director is of the opinion that the holder of the national transmission licence is not taking all or some of the steps required to collect the amount, the Director may collect that amount by way of realising the guarantees furnished by the installer of the installation or the licence holder pursuant to the provisions of its licence, if such have been furnished, or in any other manner pursuant to the provisions of this Law and pursuant to any law; funds collected as aforesaid shall be deposited in the account from which the compensation was paid in accordance with subsection (e).
(g)Where the installer of the installation as referred to in subsection (f) is the holder of the national transmission licence, the holder of the national transmission licence shall deposit in the account referred to in subsection (e), within one month from the day of commencement of construction of the installation, an amount equal to the compensation funds paid in respect of the harm from the part of the plan intended for the installation as referred to in that subsection, plus linkage differentials from the day of payment of the compensation to the date of deposit of that amount, and shall notify the Director of the Authority thereof in writing, together with a detailed calculation of the deposited amount; the Director of the Authority shall confirm in writing the amount of the reimbursement and its conditions.
(h)Where an owner of real property has submitted a claim for payment of compensation pursuant to this section to the holder of the national transmission licence and the compensation has not yet been paid or has been paid only in part, and another party has commenced the construction of an installation by virtue of the plan, that other party may replace the holder of the national transmission licence in continuing to conduct the proceedings for the purpose of paying the compensation or the balance of the compensation, as the case may be; however, in respect of compensation paid by the holder of the national transmission licence, the provisions of subsection (f) shall continue to apply.
(i)Where the Council has set conditions and provisions as referred to in subsection (e) in respect of expenses incurred by the holder of the national transmission licence for the purpose of complying with the provisions of this subsection, the provisions of subsections (f) to (h) shall also apply in respect of such expenses, with the necessary modifications.

Joinder of a Party§

29.

The licence holder, and in respect of the proviso to section 28(c) – the representative of the State, shall be invited to every hearing in proceedings pursuant to section 28 before the local committee, the appeals committee, the determining appraiser and the court, and in any other proceeding in the matter of compensation pursuant to section 197 of the Planning and Building Law, and shall be, at its request, a party to any such proceeding and to any agreement in connection therewith.

Diversion of an Existing Infrastructure Line§

30.
(a)Where the construction of a gas installation necessitated the diversion of an existing infrastructure line, the provisions prescribed by the Minister on this matter shall apply, generally or for types of cases or for a specific case.
(b)Where the owner of the infrastructure line has not carried out the provisions that it was required to carry out pursuant to subsection (a), the Minister may carry them out personally or through others, including through the licence holder.
(c)The licence holder shall bear the cost of constructing the new line and cancelling the existing line, unless the Minister has determined otherwise for special reasons; in the absence of agreement on the cost, the Director shall decide on the cost after having given the licence holder and the owner of the infrastructure line an opportunity to present their arguments.
(d)In this section, "infrastructure line" – an above-ground or underground line for the transmission or conveyance of electricity, telecommunications, water, sewage, crude oil or petroleum products.