Israeli Legislation.com
RegulationsCriminal Law

Ports Regulations (Harmful Liquid Substances in Bulk), 5776-2016

תקנות הנמלים (חומרים נוזליים מזיקים בצובר), תשע"ו-2016

Published: 2016-07-26Consolidated Hebrew text as of 2026-10-25 · Last amended 2021-09-14
Premium
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More

This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.

Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.

The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.

This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.

Section D: Maintenance of the Seaworthiness of the Vessel

Maintenance of the Seaworthiness of the Vessel§
18.

The owner of the vessel or its master shall maintain the vessel and its equipment so that they fully comply with the provisions of these Regulations, in such manner that the vessel shall remain fit in all respects to proceed to sea without presenting an unreasonable threat of harm to the marine environment.

Prohibition of Making Material Alterations to a Vessel after the Completion of a Survey§
19.

After the completion of any survey required under Section B, the owner of the vessel or its master shall not make any material alteration to the structure, equipment, systems, fittings, arrangements or materials that were surveyed without the approval of the Director; for the purposes of this regulation, a like-for-like replacement of equipment and fittings as aforesaid shall not be regarded as a material alteration.

Section E: Duty to Report an Accident or Material Defect in a Vessel

Reporting an Accident or Material Defect and Opening of an Investigation§
20.
(a)Where an accident has occurred or a defect has been discovered which materially affects the integrity of the vessel, or the efficiency or integrity of the equipment surveyed in the surveys under Section B, the owner of the vessel or its master shall report this without delay, by the fastest means available, to the Director and to the recognised organisation, as the case may be; the report shall be as detailed in regulation 98(b) of the Ports Regulations (Shipping Safety).
(b)If the vessel is in a port of a State that is a party to the Convention, the master or the owner of the vessel shall also report this to the authorities of the port State.
(c)Where the Director has received a report as provided in sub-regulation (a), he shall direct that an investigation be opened; regulations 99 to 101 of the Ports Regulations (Shipping Safety) shall apply to such an investigation.

Chapter IV: International Certificate for the Prevention of Pollution from the Carriage of Harmful Liquid Substances in Bulk

Section A: Issue of the Certificate

Issue of the Certificate§
21.

The Director shall issue to an Israeli vessel an International Certificate for the Prevention of Pollution from the Carriage of Harmful Liquid Substances in Bulk after the authorised surveyor has found, in an initial survey or a renewal survey, that it fully complies with the requirements of these Regulations.

The Certificate§
22.

The certificate shall be drawn up as set out in the First Schedule, in the Hebrew language, including a translation of its contents into the English language; in the event of any discrepancy or contradiction, the Hebrew language shall prevail.

Issue of a Certificate by Another Body§
23.

Without derogating from the Director's authority to issue the certificate under regulation 21, the Director may request a recognised organisation or a foreign state that is a party to the Convention to carry out the survey of the vessel, and where it is found that all the requirements in respect thereof have been fulfilled, to issue the certificate to it.

Section B: Duration and Validity of the Certificate

Limitation of the Period of Validity of the Certificate§
24.

A certificate shall be issued for a period to be determined by an authorised surveyor, as the case may be, which shall not exceed five years from the date of its issue.

Certificate Valid for Five Years§
25.

Notwithstanding the provisions of regulation 24 –

(1)where the renewal survey is completed within 3 months before the expiry of the existing certificate, the new certificate shall be valid from the date of completion of the renewal survey for a period not exceeding 5 years from the date on which the existing certificate expired;
(2)where the renewal survey is completed after the expiry of the existing certificate, the new certificate shall be valid from the date of completion of the renewal survey for a period not exceeding 5 years from the date on which the existing certificate expired;
(3)where the renewal survey is completed more than 3 months before the expiry of the existing certificate, the new certificate shall be valid from the date of completion of the renewal survey for a period not exceeding 5 years from the date of completion of the renewal survey.
Extension of a Certificate Valid for Less than 5 Years§
26.

Where a certificate has been issued for a period of less than five years, an authorised surveyor may extend the validity of the certificate beyond its expiry for the maximum period specified in regulation 24, provided that the authorised surveyor is satisfied that the annual surveys and the intermediate survey have been carried out.

Extension of a Certificate where a New Certificate Cannot Be Issued or Delivered§
27.

Where a renewal survey has been completed and it is not possible to issue a new certificate or to deliver it to the vessel before the expiry of the existing certificate, an authorised surveyor may extend the validity of the certificate, provided that the extension of validity shall not exceed 5 months from the expiry of the existing certificate.

Extension of a Certificate where the Vessel is not at the Port of Survey§
28.
(a)If on the date of expiry of the certificate the vessel is not at the port at which it is due to undergo a survey, an authorised surveyor may extend the validity of the certificate, provided that all of the following conditions are met:
(1)the extension is required to enable the vessel to complete its voyage to the port at which it is due to undergo a survey;
(2)the Director is satisfied that it is reasonable and proper to do so.
(b)The extension shall be granted for a period not exceeding 3 months.
(c)Where an extension has been granted to a vessel as referred to in sub-regulation (a), upon the vessel's arrival at the port at which it is due to undergo a survey, it shall not be entitled by virtue of that extension to leave the port without a new certificate.
(d)Upon completion of the renewal survey, the new certificate shall be valid for the period determined by the authorised surveyor, not exceeding 5 years from the date of expiry of the existing certificate prior to the grant of the extension.
Extension of a Certificate for a Vessel Engaged in Short Voyages§
29.

An authorised surveyor may extend the validity of a certificate issued to a vessel engaged in short voyages, which has not been extended in accordance with regulations 26, 27 and 28, for a period not exceeding one month from the date of expiry of the existing certificate; upon completion of the renewal survey, the new certificate shall be valid for the period determined by the authorised surveyor, not exceeding 5 years from the date of expiry of the existing certificate prior to the grant of the extension.

Extension of a Certificate in Special Circumstances§
30.

The determination of the validity of a new certificate under regulations 25(1) and (2), 28 and 29 shall not apply in special circumstances as determined by the Director; in such special circumstances, the new certificate shall be valid for the period directed by the authorised surveyor, not exceeding 5 years from the date of completion of the renewal survey.

Completion of Surveys before the Due Date§
31.

If an annual survey or an intermediate survey is completed before the periods specified in regulations 10 or 11, as the case may be, the following provisions shall apply:

(1)the anniversary date shown on the certificate shall be amended to a date that is not more than 3 months after the date of completion of the survey;
(2)the subsequent annual survey or intermediate survey shall be completed at the intervals specified in regulations 10 or 11, as the case may be, using the amended anniversary date;
(3)the expiry date may remain unchanged, provided that an annual survey or an intermediate survey, as the case may be, is carried out so that the maximum intervals prescribed in regulations 10 or 11, as the case may be, are not exceeded.
Expiry of the Certificate§
32.

A certificate issued under regulation 21 or 23 shall cease to be valid if any of the following has occurred:

(1)the surveys, as the case may be, have not been completed within the periods specified in Chapter III, Section B;
(2)one of the annual surveys or the intermediate survey has not been endorsed on the certificate;
(3)upon the transfer of an Israeli vessel to a foreign flag.
Issue of a New Certificate to a Vessel under the Israeli Flag§
33.

Where a vessel has been registered in the Israeli Register, the Director shall issue a new certificate to it under regulations 21 or 23.

Provisions concerning a Chemical Tanker§
34.

Notwithstanding the provisions of Chapter III and this Chapter, a chemical tanker to which a certificate has been issued under the provisions of the International Bulk Chemical Code or the Bulk Chemical Code, as the case may be, by a state that is a party to the Convention, shall be deemed to have complied with these Regulations, and the validity of the certificate issued to it under that Code shall be equivalent to the validity of the certificate issued under this Chapter.

Chapter V: Design, Construction, Arrangement, Equipment and Operation of a Vessel

Section A: General

Design, Construction, Arrangement, Equipment and Operation of a Vessel§
35.
(a)To minimise the uncontrolled discharge into the sea of harmful liquid substances in bulk, the owner of the vessel and its master shall ensure that the design, construction, equipment and operation of a vessel authorised to carry harmful liquid substances in bulk as defined in Chapter 17 of the International Bulk Chemical Code shall be as follows:
(1)in respect of a chemical tanker constructed on or after 1 July 1986 – in accordance with the International Bulk Chemical Code (IBC Code);
(2)in respect of vessels whose contract of construction was concluded on or after 2 November 1973 but which were constructed before 1 July 1986 and which are engaged in voyages to ports or terminals under the jurisdiction of other states that are parties to the Convention, and also in respect of vessels constructed on or after 1 July 1983 but before 1 July 1986 and engaged exclusively in voyages within the coastal waters or internal waters of Israel, or in the maritime zone – in accordance with section 1.7.2 of the Bulk Chemical Code (BCH Code);
(3)in respect of vessels whose contract of construction was concluded before 2 November 1973 and which are engaged in voyages to ports or terminals under the jurisdiction of other states that are parties to the Convention, and also vessels constructed before 1 July 1983 and engaged exclusively in voyages between ports or terminals within the coastal waters or internal waters of Israel, or in the maritime zone – in accordance with section 1.7.3 of the Bulk Chemical Code (BCH Code).
(b)Vessels other than chemical tankers or liquefied gas carriers, authorised to carry harmful liquid substances in bulk identified in Chapter 17 of the International Bulk Chemical Code – as set out in IMO Assembly Resolution A.673(16), as amended by Resolutions MEPC.158(55) and MEPC.148(54).

Section B: Pumping, Piping and Slop Tank Arrangements

Pumping, Piping and Discharge Outlet Arrangements§
36.

The owner of the vessel and its master shall equip the vessel with pumping, piping and discharge outlet arrangements as set out in the Second Schedule.

Pumping Efficiency Tests§
37.
(a)An authorised surveyor shall inspect the pumping and piping arrangements referred to in items (1) to (3) of the Second Schedule by means of pumping efficiency tests as provided in the Authority's procedure; the Authority's procedure under this regulation shall be based on Appendix 5 to the Annex (hereinafter – the pumping efficiency test procedure).
(b)In pumping efficiency tests, water shall be used as the test medium.

Section C: Discharge Arrangements

Regulation of Discharge§
38.
(a)Discharge into the sea of residue, a mixture of water with residue, ballast water, tank washing water or other mixtures containing such substances is prohibited, unless it is carried out in accordance with the following provisions:
(1)before carrying out any discharge procedure or prewash, the tank in question shall be emptied as thoroughly as possible as set out in the Procedures and Arrangements Manual;
(2)prewashing of the tanks and ventilation thereof, if required under the Third Schedule, shall be carried out in accordance with the Authority's procedures which shall be based on Appendix 6 to the Annex with respect to prewashing (hereinafter – the prewash procedure), and on Appendix 7 to the Annex with respect to ventilation (hereinafter – the ventilation procedure);
(3)the discharge shall be carried out as set out in the Third Schedule.
(b)An authorised surveyor shall verify that a discharge as referred to in sub-regulation (a) has been carried out as set out in the Third Schedule.
Exemption from Prewashing§
39.
(a)At the request of the master of the vessel, the Director may grant an exemption to a vessel engaged in voyages to ports or terminals under the jurisdiction of a state that is a party to the Convention from the prewashing requirements for tanks as referred to in this Section, in whole or in part, if satisfied that one of the following applies:
(1)the unloaded tank is intended to be reloaded with the same substance or with another substance compatible with the previous substance, provided that the tank shall not be washed or filled with ballast water prior to loading;
(2)the unloaded tank has not been washed and has not been filled with ballast water at sea; the prewashing referred to in this Section shall be carried out at another port, provided that the Director has been satisfied that written approval has been given by the competent authority at that port confirming that a reception facility exists at that port and is suitable for the said purpose;
(3)the cargo residues shall be removed as set out in the ventilation procedure.
(b)In respect of an Israeli vessel, the Director may grant an exemption as referred to in sub-regulation (a) only when the vessel is in the coastal waters of Israel.
Exceptions to the Regulation of Discharge§
40.

The discharge requirements under this Section shall not apply to the discharge into the sea of any of the following:

(1)ballast water, bilge water, other residues or mixtures containing only other substances, within the meaning of regulation 4(d);
(2)clean or segregated ballast water;
(3)harmful liquid substances or mixtures containing such substances if one of the following applies:
(a)the discharge is necessary for the purpose of saving life at sea or ensuring the safety of the vessel;
(b)the discharge results from damage to the vessel or its equipment, provided that all reasonable precautions have been taken after the occurrence of the damage or the identification of the discharge in order to prevent or minimise the discharge, and the owner of the vessel or its master did not act with intent to cause damage, or recklessly and with knowledge that damage would probably result;
(c)a discharge approved by the Authority in consultation with the Director of the National Unit for the Protection of the Marine Environment in the Ministry of Environmental Protection, for the purpose of combating a pollution incident in order to minimise the damage caused by the pollution; any such discharge shall be subject to the approval of every competent authority within whose jurisdiction the discharge is expected to take place.

Chapter VI: Equivalents

Equivalents§

41.
(a)The Director may permit the installation of any fitting, material of construction, appliance or apparatus as a substitute for those required under these Regulations, provided that such substitutes are not inferior in effectiveness to what is required under these Regulations; a permit as aforesaid may be subject to conditions as the Director shall direct.
(b)The Director's authority as referred to in sub-regulation (a) shall not apply if, as a result of granting the permit referred to in sub-regulation (a), it would be necessary to prescribe alternative operational methods affecting the control or discharge of harmful liquid substances in respect of the properties, design, construction, arrangement and operation of vessels under regulation 35(a)(1) to (3).
(c)Notwithstanding the provisions of sub-regulations (a) and (b), in respect of a vessel carrying liquefied gas and authorised to carry harmful liquid substances in bulk (hereinafter – gas vessel), the equipment and construction requirements set out in the International Code for the Construction and Equipment of Ships Carrying Liquefied Gases in Bulk (IGC Code) referred to in item 15 of the Seventeenth Schedule to the Ports Regulations (Shipping Safety) (hereinafter – IGC Code) shall be regarded as equivalent to the codes referred to in regulation 35(a)(1) to (3), provided that the owner and master of the vessel have equipped the gas vessel with all of the following:
(1)a certificate of fitness in accordance with the IGC Code;
(2)a certificate stating that the vessel is permitted to carry only the harmful liquid substances in bulk as defined in the IGC Code;
(3)segregated ballast tanks;
(4)pumping and piping arrangements approved by the Director, after he has satisfied himself that the quantity of cargo residues that will remain in the tank and its associated piping after discharge will not exceed the quantities set out in item (1)(a)(1) to (3) of the Second Schedule;
(5)a manual approved by the Director, after he has satisfied himself that its contents are designed to ensure that no operational mixing of cargo residues and water occurs and that no cargo residues remain in the tank after the ventilation procedures set out in the manual have been carried out.