תקנות למניעת מפגעי אסבסט ואבק מזיק (פטור מרישיון ומהיתר לעבודת אסבסט ומניעת ניגוד עניינים), תשע"א-2011

Published: 2011-08-29Consolidated Hebrew text as of 2024-09-20 · Last amended 2020-05-21
Premium
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More

This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.

Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.

The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.

This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.

By virtue of my powers under sections 14(b)(2), 34(d), 36(b) and 78 of the Law for the Prevention of Asbestos and Harmful Dust Hazards, 5771-2011 (hereinafter – the Law), and with the approval of the Interior and Environmental Protection Committee of the Knesset, I hereby promulgate these Regulations:

Definitions§

1.

In these Regulations –

"business day" – any day of the week, excluding Friday, a day of rest as defined in section 18a(a) of the Law and Administration Ordinance, 5708-1948, and the eve of such a day of rest, an intermediate day of a festival (chol ha-moed), and a day of rest prescribed by statute;

"building designated for demolition" – a building which, according to a confirmation by the work orderer under regulation 4b(3), is not intended for use after the dismantling and removal work of asbestos-cement products from it, but is designated for demolition;

"partition wall" – a complete and sound rigid partition made of an impermeable building material;

"low-risk work" – dismantling and removal work of asbestos-cement products and their clearance and transport for burial, in respect of which the conditions set out in paragraphs (1), (3) and (4) of the definition of "limited work" are met, with the necessary modifications, and which is one of the following:

(1)dismantling and removal work of asbestos-cement sheets (hereinafter – sheets) whose total area does not exceed 500 square metres, or of an asbestos-cement pipe (hereinafter – pipe) whose total length does not exceed 100 metres, carried out in a building designated for demolition or in an open shed;
(2)clearance of a pile of asbestos-cement waste of a scope not exceeding 500 square metres of sheets or 5 tonnes of another asbestos-cement product, as well as transport of such a pile for burial; for this purpose, "pile" – a concentration of sheets or another asbestos-cement product, which are in a complete and sound condition, placed one on top of the other or adjacent to one another;
(3)dismantling and removal work of sheets in a building, provided that the total area of the sheets does not exceed 100 square metres, that there is a partition wall between the sheets and the interior of the building, and that the openings of the building can be closed;

"limited work" – dismantling and removal work of sheets or a pipe, as well as their clearance and transport for burial, in which all of the following are met:

(1)the building in which the work is carried out (hereinafter in this definition – the building) is not a public place as referred to in paragraph (1) of the definition of "public place" in the Law;
(2)the total area of sheets in the building does not exceed 50 square metres and the total length of the pipe in the building does not exceed 10 metres;
(3)the sheets or pipe are not burnt and are not cracked, broken, or damaged to an extent exceeding one third of the quantity of asbestos-cement installed in the building;
(4)the sheets or pipe can be removed from the building in their entirety and without damaging the sheets or the pipe, as the case may be;

"clearance of an asbestos product" – removal from a property of a complete and sound asbestos product whose weight does not exceed 700 kilograms, which has not been dismantled and is not fixed to the ground, to a building or to a vehicle, and its transport for burial.

Exemption from Licence and Permit for Limited Work and for Clearance of an Asbestos Product§

2.

A person may carry out limited work or clearance of an asbestos product in a property owned by or in the possession of that person, intended for that person's use (hereinafter – the owner), by himself or herself or by another person carrying out the work on that person's behalf without consideration or by that person's employee (hereinafter – the performer), even if that person or the performer does not hold a licence appropriate for carrying out asbestos work, and such work shall be exempt from obtaining a permit for asbestos work, provided that all of the following conditions are met in respect of the owner and the performer:

(1)the owner and the performer have not carried out limited work without a permit during the two years preceding the carrying out of that limited work;
(2)the owner and the performer are adults.

Duties, Restrictions and Conditions for the Carrying Out of Limited Work§

3.

The carrying out of limited work, as referred to in regulation 2, shall be subject to the duties, restrictions and conditions set out below, which shall apply to the owner and the performer, as the case may be:

(1)notice in the form detailed in the First Schedule shall be delivered to users present in properties adjoining the work area; the notice shall be delivered in writing at least two days before the carrying out of the limited work; in work carried out in a property adjoining a public place as referred to in paragraph (1), (2) or (6) of the definition of "public place" in the Law, the asbestos work shall be carried out at hours and times when no persons are present in the public place and after delivery of notice as aforesaid to the person in possession of it;
(2)notice in the form prescribed in the First Schedule shall be posted in conspicuous places on the property at least 24 hours before the commencement of the work;
(3)entry by persons who are not the owner, the performer or a person supervising the work pursuant to law into the work area shall be prevented, from the commencement of the work until its completion;
(4)in work carried out in a building, air conditioners and ventilation systems operated by drawing external air shall be switched off throughout the duration of the carrying out of the work, and in addition –
(a)if there is a partition wall between the asbestos-cement and the interior space of the building – the openings of the building shall be closed from the commencement of the work until its completion;
(b)if there is no partition wall between the asbestos-cement and the interior space of the building – objects present in the building shall be removed before the commencement of the work, and if they cannot be removed – such objects shall be covered with polyethylene sheets as protection against dust liable to be generated during the course of the work; the sheets shall be removed after the completion of the work and the cleaning of the work site and shall be cleared as asbestos waste;
(5)the asbestos-cement components shall be wetted with water or with a water-based binding agent immediately before the commencement of dismantling in order to prevent the creation of visible dust and the dispersal of asbestos fibres during the course of the work;
(6)the work shall be carried out continuously and within the shortest possible period of time;
(7)those present during the carrying out of the work shall use respiratory protection equipment and disposable work clothing (hereinafter in this regulation – protective equipment);
(8)asbestos-cement components shall be removed in their entirety by releasing or cutting the screws connecting them, manually, without breaking and without the use of electric cutting tools;
(9)dismantled asbestos-cement components shall be wrapped in their entirety in two layers of impermeable polyethylene and fastened with adhesive tape;
(10)upon completion of the work, asbestos-cement residues shall be collected from the work site, and likewise protective equipment used in the carrying out of the work and polyethylene sheets used to protect objects and equipment shall be wrapped in two layers of impermeable polyethylene and fastened with adhesive tape; measures shall also be taken to verify the absence of asbestos at the work site and its surroundings upon completion of the work, including cleaning of the work site of asbestos and including cleaning of parts of the building and objects present at the work site;
(11)the inscription "Danger! Contains asbestos waste" shall be added in black on the asbestos wrappings, clearly and conspicuously;
(12)asbestos waste as referred to in paragraphs (9) and (10) shall be cleared to an asbestos waste site holding an asbestos waste site operator's licence under section 22 of the Law, for burial, and the asbestos shall be wrapped and packaged in a manner that prevents its dispersal;
(13)the owner and the performer of the work shall retain a copy of the notice referred to in paragraph (1) and documentation of the methods of its delivery, and shall also retain a copy of a confirmation of receipt of asbestos waste issued to them by an asbestos waste site to which they cleared asbestos waste pursuant to paragraph (12), all for a period of at least three years from the carrying out of the limited work.

Duties, Restrictions and Conditions for the Clearance of an Asbestos Product§

4.

The carrying out of clearance of an asbestos product, as referred to in regulation 2, shall be subject to the duties, restrictions and conditions set out below, which shall apply to the owner and the performer, as the case may be:

(1)the asbestos in the product shall be wetted with water or with a water-based binding agent immediately before the clearance;
(2)the asbestos product shall be cleared in its entirety, without cutting and without breaking;
(3)the asbestos product shall be wrapped in two layers of polyethylene fastened with adhesive tape in a manner that prevents the dispersal of asbestos, and the inscription "Danger! Contains asbestos waste" shall appear on the wrapping in black, clearly and conspicuously;
(4)the asbestos product shall be cleared to an appropriate asbestos waste site, for burial.

Exemption from Permit for an Asbestos Contractor for Limited Work and for Clearance of an Asbestos Product§

4a.

An asbestos contractor (in this regulation – the contractor) may carry out limited work or clearance of an asbestos product (in this regulation – the work) without a permit for asbestos work, provided that all of the following are met:

(1)the contractor shall carry out the work in a manner that prevents risk to the public and to the environment, using equipment and instruments appropriate for the work, and shall act in accordance with the provisions of section 39 of the Law, subject to the modifications and conditions prescribed in this regulation;
(2)the contractor's responsible worker shall notify the supervisor in writing, by means of an online form available on the website of the Ministry of Environmental Protection (hereinafter – online form), of the intention to carry out the work, at least three business days before its carrying out, and shall state in the notice all of the following: the precise location of the work site, the nature of the use of the property or building in which the work is to be carried out, the work plan, the work method and a planned date for carrying out the work, the full name of the work orderer and of the owner of the property or building or the person in possession of it and their contact details;
(3)the following shall be attached to the notice referred to in paragraph (2): at least two photographs of the work site, a declaration signed by the contractor's responsible worker confirming that the conditions for exemption from a permit pursuant to this regulation are met, the contractor's written undertaking to comply with the conditions for carrying out the work, and a confirmation from the work orderer regarding the details of the property for which the work was ordered as they appear in the notice;
(4)the contractor shall carry out the work within half a year from the date of the notice, subject to the provisions of regulation 4c, provided that if the work is to be carried out on a date different from the planned date stated in the notice pursuant to paragraph (2), the contractor shall give written notice, by means of an online form, of the new date at least 48 hours before the carrying out of the work;
(5)before carrying out the work, the contractor shall, through the contractor's responsible worker, brief the contractor's workers regarding the carrying out of the work in a manner that prevents risk to the public and to the environment, and during the work the contractor shall, personally and through the contractor's responsible worker, supervise the carrying out of the work by the contractor's workers;
(6)the work shall be carried out in accordance with the details provided in the notice referred to in paragraph (2), including in accordance with the work plan; however, if a change to the work plan or to such details is required, the contractor shall report this to the supervisor, in writing and immediately, by means of an online form; the report shall be made in advance, but if this was not possible, the report shall be made after the fact, as close as possible to the time the change occurred;
(7)the contractor shall carry out the work in accordance with the requirements concerning limited work under regulation 3(1), (2), (4) to (6), (8) and (12) or in accordance with the requirements concerning clearance of an asbestos product under regulation 4(1), (2) and (4), as the case may be, with the necessary modifications and with this modification: in regulation 3(4)(b), it shall be read as if instead of "shall be covered with polyethylene" it said "shall be covered with two layers of polyethylene sheeting";
(8)during the work, entry by persons who are not the contractor's workers or persons supervising the work pursuant to law into the work site shall be prevented;
(9)upon completion of the work, all asbestos waste shall be collected from the work site for the purpose of its clearance; in this regulation, "asbestos waste" – including asbestos-cement residues present at the work site, protective equipment used in the carrying out of the work, polyethylene sheets used to protect objects and equipment, and also equipment, objects and building materials contaminated with asbestos that cannot be cleaned of asbestos;
(10)the asbestos waste shall be packaged, during the course of the work and before clearance, in dedicated industrial packaging within the confines of the work site; in this paragraph, "dedicated industrial packaging" – packaging in which all of the following are met:
(a)it has appropriate carrying and lifting capacity and has double walls and carrying handles;
(b)an asbestos warning sign is embossed on it, and the name and licence number of the contractor who carried out the work are stated on the packaging;
(c)it meets the conditions of packaging from group 2 or 3 pursuant to the Transportation Services Regulations, 5761-2001;
(11)upon completion of the work, the contractor shall carry out a visual inspection to verify that no asbestos remains at the work site and its surroundings, and where necessary shall ensure that the work site, including parts of the building and objects present at the work site, is cleaned of asbestos; the asbestos waste shall be cleared from the work site as early as possible and no later than 48 hours from the completion of the work;
(12)upon completion of the work, the contractor shall provide the work orderer with a confirmation that the conditions for completion of the work as referred to in paragraph (11) are met, for the purpose of re-occupation of the property or building, as the case may be;
(13)the contractor shall retain all documents recording the carrying out of the work pursuant to the provisions of these Regulations, including a confirmation of the clearance of asbestos waste to an asbestos waste site, for a period of at least three years from the date of carrying out the work.

Exemption from Permit for an Asbestos Contractor for Low-Risk Work§

4b.

An asbestos contractor (in this regulation – the contractor) may carry out low-risk work (in this regulation – the work) without a permit for asbestos work, provided that all of the following are met:

(1)the contractor shall carry out the work in a manner that prevents risk to the public and to the environment, using equipment and instruments appropriate for the work, and acts in accordance with the provisions of section 39 of the Law, subject to the modifications and conditions prescribed in this regulation;
(2)the contractor's responsible worker has notified the supervisor in writing, by means of an online form, of the intention to carry out the work, at least five business days before its carrying out, and has stated in the notice all of the following: the precise location of the work site, the nature of the use of the property or building in which the work is to be carried out, the work plan, the work method and a planned date for carrying out the work, the full name of the work orderer and of the owner of the property or building or the person in possession of it and their contact details;
(3)the notice referred to in paragraph (2) shall state the existence of a partition wall, if one exists, and the following shall also be attached to the notice: at least two photographs of the work site, a drawing of the work site and its surroundings within a distance of 50 metres from the work site, a declaration signed by the contractor's responsible worker confirming that the conditions for exemption from a permit pursuant to this regulation are met, the contractor's written undertaking to comply with the conditions for carrying out the work, and a confirmation from the work orderer regarding the details of the property for which the work was ordered as they appear in the notice;
(4)the contractor shall post notice in the form prescribed in the Second Schedule in conspicuous places on the property in which the work is being carried out and on properties situated within a distance of up to 50 metres from the work site, at least two days before the commencement of the work;
(5)in work carried out within a distance not exceeding 50 metres from a public place, the contractor shall carry out the work at hours and times when no persons are present in the public place, and after giving notice to the person in possession of it;
(6)the contractor shall carry out the work in accordance with the requirements under regulation 3(4), (5), (6), (8) and (12) and under regulation 4a(4), (5), (6) and (8) to (13).

Restriction on Exemption from Obtaining an Asbestos Work Permit§

4c.
(a)Notwithstanding the provisions of regulations 4a and 4b, an asbestos contractor shall not carry out limited work, clearance of an asbestos product or low-risk work without an asbestos work permit, if the supervisor has notified the asbestos contractor, within the period from the date of the notice referred to in regulation 4a(2) or 4b(2), as the case may be (hereinafter – the contractor's notice), until the date of carrying out the work as stated in the contractor's notice or until the actual date of carrying out the work, whichever is the later, that the work or the clearance requires an asbestos work permit, after finding that the details provided in the asbestos contractor's notice are incomplete, or after finding that there is a risk in the work or the clearance, or that there is a need to conduct a further inquiry regarding the work or the clearance, inter alia, for the purpose of assessing their level of risk.
(b)Without derogating from the power under sub-regulation (a), the Director may instruct, if satisfied that an asbestos contractor has provided false, misleading, incorrect or partial information to the Director or to the supervisor, including in the framework of a notice under regulation 4a or 4b or in a report under section 39(b)(3) of the Law, or that the contractor has not fulfilled the contractor's obligations under these Regulations, in whole or in part, that the asbestos contractor shall not be entitled to carry out work pursuant to the provisions of the said Regulations for a period of up to one year, as the Director shall instruct.

Exemption from Licence for Maintenance Work in an Industrial Installation§

5.
(a)The owner of an industrial installation or the person in possession of it may carry out repair of a partition as referred to in section 5(e) of the Law, personally or through employees, even if that person or the employees do not hold a friable asbestos contractor's licence, provided that that person holds a permit for the asbestos work and the work is carried out in accordance with the conditions of the permit.
(b)The owner of an active industrial installation or the person in possession of it may carry out, personally or through employees, the removal and clearance of thermal insulation containing asbestos weighing not more than 10 kilograms, required as a result of an incident in which the thermal insulation or the partition was damaged during the routine operation of the industrial installation, even if that person or the employees do not hold a friable asbestos contractor's licence, provided that that person holds a permit for the asbestos work and the work is carried out in accordance with the conditions of the permit.

Exemptions from Licence for Asbestos Removal in the Israel Defence Forces§

6.
(a)The Israel Defence Forces may carry out work to remove brake pads containing asbestos from vehicles pursuant to section 7 of the Law, through its workers, even if it or its workers do not hold a friable asbestos contractor's licence, provided that all of the following are met:
(1)the said pads are immersed in oil and are contained in a closed assembly, separated from the interior space of the vehicle;
(2)it holds a permit for the asbestos work and the work is carried out in accordance with the conditions of the permit;
(3)the worker carrying out the said work is not a conscript soldier as defined in the Israel Defence Forces (Permanent Service) (Benefits) Law [Consolidated Version], 5745-1985, and is not a reservist soldier as referred to in paragraph (2) of the definition of "soldier" in the Military Justice Law, 5715-1955, has given written consent to carry out the said work, and has participated in dedicated training for this purpose that the Director has approved;
(4)before the carrying out of the work, workers who are about to carry it out shall be given instruction regarding the hazards involved in working with asbestos and the protective and precautionary measures required in the carrying out of the work.
(b)(Repealed)
(c)For the purpose of this regulation, "workers" – including those serving in the Israel Defence Forces and those working in its service.

Conflict of Interests of a Work Orderer who is an Asbestos Contractor or a Friable Asbestos Supervisor§

7.

The carrying out of friable asbestos work by a work orderer as defined in section 37(a) of the Law (hereinafter – the orderer), who is an asbestos contractor or a friable asbestos supervisor, or by the orderer's employee who is a contractor or supervisor as aforesaid, shall be regarded as circumstances in which a conflict of interests of a person engaged in asbestos is liable to arise, unless the work is in a property owned by or in the possession of the orderer, provided that in that work, in addition to the orderer or the orderer's employee, a friable asbestos contractor or a friable asbestos supervisor, as the case may be, as well as a sampling laboratory, none of whom is the orderer or the orderer's employee, shall also be employed.

Conflict of Interests of a Sampling Laboratory and an Asbestos Sampler§

8.

The carrying out of air sampling in asbestos work by a sampling laboratory or an asbestos sampler who serve an asbestos contractor, a responsible worker or a friable asbestos supervisor in the same work, as well as the employment of a sampling laboratory or an asbestos sampler by an asbestos contractor, a responsible worker or a friable asbestos supervisor or payment to a sampling laboratory or an asbestos sampler by an asbestos contractor, a responsible worker or a friable asbestos supervisor, shall be regarded as circumstances in which a conflict of interests of a person engaged in asbestos is liable to arise.

Page 1 of 2

Read the entire law on one page — continuous text, no page breaks, plus formal citations.

RegulationsHealthEnvironment

תקנות למניעת מפגעי אסבסט ואבק מזיק (פטור מרישיון ומהיתר לעבודת אסבסט ומניעת ניגוד עניינים), תשע"א-2011

asbestos dust regulations 2011

asbestos hazards prevention regulations

asbestos licensing exemption regulations

takkanot asbestos avak regulations

harmful dust prevention law Israel

asbestos work permit regulations

conflict of interest asbestos regulations

asbestos exemption regulations 5771

occupational asbestos hazards Israel

asbestos dust control regulations