Contractors Registration for Civil Engineering Works (Classification of Registered Contractors) Regulations, 5748-1988
תקנות רישום קבלנים לעבודות הנדסה בנאיות (סיווג קבלנים רשומים), תשמ"ח-1988
Unofficial English translation — for reference only. It may contain errors or omissions and cannot be relied on as a legal text. Only the Hebrew text published in Reshumot is legally binding.More
This English text was translated from the official Hebrew using a range of translation tools, and it undergoes ongoing checks and updates. It is not a certified translation.
Despite these checks, it may contain errors, omissions, or imprecise renderings of legal terminology and cross-references, and it may not yet reflect the latest amendments. It cannot be relied upon as a legal text.
The Hebrew text as published in Reshumot (ספר החוקים) and on the Knesset website is the sole authoritative and legally binding version. In any discrepancy, the Hebrew text prevails.
This translation is provided for informational purposes only and does not constitute legal advice. For use in legal proceedings, request a certified Expert Legal Opinion.
By virtue of my authority under Sections 7(a)(3) and 17 of the Contractors Registration for Civil Engineering Works Law, 5729-1969 (hereinafter – the Law), and after consultation with the Council, I hereby make these Regulations:
Definitions§
In these Regulations –
"classification" – division according to one of the types in the groups specified in the First Schedule for a main branch or sub-branch in which the contractor is registered;
"type" –
"works at a single site" – (Repealed)
"works of the required scope" – civil engineering works in which one of the following two conditions is met:
"index" – the residential construction inputs index published by the Central Bureau of Statistics;
"control" – the direct holding of a majority of the issued share capital, a majority of the voting power, the right to receive a majority of the profits and the right to appoint a majority of the directors.
Classification of Registered Contractors§
A person who is registered in the register after the commencement of these Regulations shall be classified by the Registrar in type 1.
Conditions for Change of Classification§
Classification in the Renovation Branch§
Upgrading of Classification from Type Q§
Notwithstanding the provisions of regulation 3(a), the Registrar may upgrade the classification of a contractor classified in type Q to type 1, upon the contractor's application, if one of the following is met:
Grounds for Non-Upgrading of Classification§
Application for Change of Classification§
Index Linkage§
The amounts specified in the Schedules shall be adjusted on 1 April and on 1 October of each year (hereinafter – the adjustment date) in accordance with the rate of increase in the index, from the index last published before the previous adjustment date up to the index last published before the adjustment date; the amounts so adjusted shall be rounded up to the nearest thousand whole new shekels.
Special Type§
however, a special type as referred to in this paragraph shall not be approved for a contractor unless at least 10 years have elapsed from the day of approval of the special type as aforesaid.
(Repealed)
Classification for a Period§
1. the contractor has submitted an application to the Registrar and specified the type of work and its duration;
2. the application was accompanied by an approach from a government ministry, local authority or public corporation established by law to approve the contractor's application, given that the tender in question did not have a sufficient number of candidates;
3. the applicant is a corporation in which control is held by two or more contractors, each of whom has been classified for the two years preceding the day of submission of the application in a type lower by one type than the type for which the corporation applies to be classified, provided that the said contractors have completed the execution of works at a single site in a scope of approximately 50% or more of the maximum scope permitted in the type in which they are registered.
Receipt of Engineering Services§
A contractor whose classification has been lowered as aforesaid may apply for the classification to be upgraded to the previous type if the contractor has demonstrated that the contractor regularly receives engineering services in all of the contractor's works from a practical engineer or an engineer as required under these Regulations.
Change of Classification Granted§
2. the Registrar shall exercise the authority referred to herein only after affording the contractor an opportunity to present arguments before the advisory committee;
3. a company that was in liquidation or receivership and whose shares have been transferred to others shall not have the suspension of the classification lifted and the classification renewed except after the Registrar is satisfied that all the conditions prescribed in these Regulations have been fulfilled;
4. where a temporary or permanent receiver, a special manager or a trustee for the business of the contractor has decided to operate the company or to rehabilitate the company, with the approval of the court, the company's classification shall not be suspended, and if it has been suspended – the suspension shall be lifted pending a further decision of the court.
Follow-Up Examination§
Penalties§
The execution of civil engineering works whose scope exceeds that permitted in the type in which the contractor is classified constitutes an offence under Section 16(1) of the Law.
Repeal§
The following are repealed –
1. Contractors Registration for Civil Engineering Works (Classification of Registered Contractors) Regulations, 5744-1984 (hereinafter – the Regulations);
2. Contractors Registration for Civil Engineering Works (Classification of Registered Contractors) (Proof of Financial Capacity) Regulations, 5745-1985.
Transitional Provisions§
A contractor who received a classification under the Regulations shall continue to be registered under the same type until the change of the classification under these Regulations.
Read the entire law on one page — continuous text, no page breaks, plus formal citations.
Made under
Other regulations under the Contractors Registration for Civil Engineering Works Law
- Contractors Registration for Civil Engineering Works (Determination of Branches and Division of Branches into Sub-Branches) Regulations, 5753-1993
- Contractors Registration for Civil Engineering Works (Evidence and Examinations for Sub-Branches) Regulations, 5749-1988
- Contractors Registration for Civil Engineering Works (Financial Scope and Professional Nature) Regulations, 5744-1984
- Contractors Registration for Civil Engineering Works (Licence Fee) Regulations, 5741-1980
- Contractors Registration for Civil Engineering Works (List of Schools and Courses) Regulations, 5734-1974
- Contractors Registration for Civil Engineering Works (Registration Fees) Regulations, 5741-1980
תקנות רישום קבלנים לעבודות הנדסה בנאיות (סיווג קבלנים רשומים), תשמ"ח-1988
contractors registration regulations 1988
civil engineering contractors classification
registered contractors regulations
takkanot rishum kavlanim
contractors classification regulations
engineering works contractors
kavlanim reshomim
construction contractors registration
contractor licensing regulations israel